Solved

Two Critical Path Activities Are Candidates for Crashing on a CPM

Question 31

Multiple Choice

Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost. Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.   A) One;$400 B) One;$6,800 C) Two;$1,000 D) Two;$5,000 E) One or Two should be crashed;$1,400


A) One;$400
B) One;$6,800
C) Two;$1,000
D) Two;$5,000
E) One or Two should be crashed;$1,400

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions