Multiple Choice
Table J.3
Six jobs have just arrived at workstation 017;which has been idle.All the pertinent data are given in the following table.The shop works eight hours per day.It is now time zero.
-Use the information in Table J.3.According to the shortest processing time rule (SPT) ,which one of the following sequences is most appropriate?
A) A-B-C-D-E-F
B) E-A-B-C-D-F
C) B-C-E-D-F-A
D) D-E-F-A-C-B
Correct Answer:

Verified
Correct Answer:
Verified