Six jobs have just arrived at workstation 017;which has been idle.All the pertinent data are given in the following table.The shop works eight hours per day.It is now time zero.
-Use the information in Table J.3.According to the critical ratio (CR) rule,which one of following sequences is most appropriate?
A) F-A-D-B-E-C
B) D-B-F-E-A-C
C) A-B-D-F-E-C
D) C-D-F-B-A-E
Correct Answer:

Verified
Correct Answer:
Verified