Multiple Choice
Table J.9
There are three jobs available for processing at Workstation 1. They just arrived at Workstation 1, at the end of Day 0.
-Using the information in Table J.9 and the critical ratio rule, what should be the sequence of jobs processed at Workstation 1?
A) C-B-A
B) B-A-C
C) A-B-C
D) B-C-A
Correct Answer:

Verified
Correct Answer:
Verified