Multiple Choice
Table 16.4
Consider the following MPS,BOM,and inventory data.Blank MRP records are provided at the end of this exam.
Master Production Schedule: The following table shows the MPS start quantities. Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
-Use the information in Table 16.4.Which one of the following statements about item F is BEST?
A) The gross requirement in week 4 is 400 units.
B) Its first planned receipt is for 120 units in week 4.
C) Its 100-unit scheduled receipt in week 1 could be delayed to week 2 without delaying the planned order release for product B.
D) Its first planned order receipt is for 385 units in week 4.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Which of the following is NOT used
Q14: One thing that an MRP II system
Q55: Facilitating goods in a hotel's bill of
Q85: A materials requirements planning (MRP) explosion occurs
Q116: If the demand for an independent demand
Q121: A computer-generated memo used by inventory planners
Q122: Table 16.6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 16.6
Q123: Table 16.7<br>Viola Products produces one item with
Q130: Table 16.5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 16.5
Q131: Table 16.5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 16.5