Multiple Choice
Table 15.8
Suppose that the following five jobs must be scheduled through a car repair facility (all times are shown in days) :
-Use the information in Table 15.8.What is the average past due (in days) using the FCFS rule?
A) fewer than or equal to 2 days
B) greater than 2 days but fewer than or equal to 3 days
C) greater than 3 days but fewer than or equal to 4 days
D) greater than 4 days
Correct Answer:

Verified
Correct Answer:
Verified