Suppose that the following five jobs must be scheduled through a car repair facility (all times are shown in days) :
Table 15.8 Suppose that the following five jobs must be scheduled through a car repair facility (all times are shown in days) :    -Use the information in Table 15.8.What is the average flow time (in days) using the EDD rule? A) fewer than or equal to 8 days B) greater than 8 days but fewer than or equal to 12 days C) greater than 12 days but fewer than or equal to 16 days D) greater than 16 days
-Use the information in Table 15.8.What is the average flow time (in days) using the EDD rule?


A) fewer than or equal to 8 days
B) greater than 8 days but fewer than or equal to 12 days
C) greater than 12 days but fewer than or equal to 16 days
D) greater than 16 days