Table 15.10 a Work Center Has the Following Six Jobs Waiting to Waiting

Question 115

Multiple Choice

Table 15.10
A work center has the following six jobs waiting to be processed (all times are shown in days) :
Table 15.10 A work center has the following six jobs waiting to be processed (all times are shown in days) :    -Use the information in Table 15.10.Which job will be the first one completed if scheduling is done using the first-come,first-served (FCFS) rule? A) A B) B C) C D) D
-Use the information in Table 15.10.Which job will be the first one completed if scheduling is done using the first-come,first-served (FCFS) rule?


A) A
B) B
C) C
D) D

Correct Answer: