Use the Information in the Preceding Table and Sequence the Six

Question 154

Essay

  Use the information in the preceding table and sequence the six jobs using first come,first served (FCFS)and earliest due date (EDD).Calculate the average flow time and average past due.It is now time zero. Use the information in the preceding table and sequence the six jobs using first come,first served (FCFS)and earliest due date (EDD).Calculate the average flow time and average past due.It is now time zero.

Correct Answer:

verifed

Verified

blured image Average Flow Time = 166 ÷ 6 =...