Columbia Appliance sells and delivers appliances in the Columbia,South Carolina area.The Operations and Supply Chain Manager wants to be able to predict the delivery crew's hours for easier scheduling.The delivery crew,consisting of a truck and two workers,must load the truck each day and then drive the truck to various locations to deliver appliances.Variables each day include miles driven and the number of deliveries made.The manager has collected data for the past five weeks,and has recorded the following average daily crew hours worked,miles driven and deliveries made:
The manager uses the multiple regression model in POM for Windows and obtains the following results:
-Use the information provided in Table 14.3.If 10 extra miles of driving is added to the crew's daily work,how much time is added to their work schedule for that day? (Assume all other variables are held constant. )
A) 30 minutes
B) 2.4 minutes
C) 24 minutes
D) 48 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q57: What are reasonable criteria for selecting one
Q76: Which one of the following is most
Q78: Salesforce estimates are extremely useful for technological
Q79: A systematic increase or decrease in the
Q91: Combination forecasting is a method of forecasting
Q137: A local moving company has collected data
Q143: _ is the prediction of future events
Q144: Table 14.11<br>A sales manager wants to forecast
Q147: _ selects the best forecast from a
Q149: _ is a time-series method used to