Multiple Choice
Table 7.3 The figure above shows the process for customers arriving at Pierre's Spa and Salon.After signing in,customers are routed to different locations in the Spa for the two different services provided.The numbers in parentheses are the time in minutes for each step of the process.
-Use the information in Table 7.3.What is the throughput time for the A-B-C-D -H routing?
A) 48 minutes
B) 30 minutes
C) 53 minutes
D) 23 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q18: A competent operations manager should first eliminate
Q65: _ is the maximum rate of output
Q71: Use the process flow diagram to determine
Q72: Table 7.8<br>King Supply makes four different types
Q73: Table 7.6<br>Burdell Industries makes four different models
Q76: Table 7.4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.4
Q77: Table 7.8<br>King Supply makes four different types
Q78: Table 7.6<br>Burdell Industries makes four different models
Q79: In a shop managed according to TOC
Q98: Work should be released into the system