Multiple Choice
Instead of dividing by nc to determine the efficiency of a line balance,you could divide by:
A) the number of workers times the number of stations.
B) the number of tasks plus the number of stations.
C) the sum of the task times plus the sum of the idle times.
D) (1-balance delay) .
Correct Answer:

Verified
Correct Answer:
Verified