Multiple Choice
Table 7.14
The production of a particular product consists of seven work elements.The desired output rate is 60 units per hour.The work element and their precedence relationships are given.
-Use the information in Table 7.14.What is the most efficient line balance you can achieve?
A) less than or equal to 70%
B) more than 70% but less than or equal to 75%
C) more than 75% but less than or equal to 80%
D) more than 80%
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Figure 7.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Figure 7.1
Q4: Table 7.15<br>The Terminal Company is attempting to
Q4: How can Theory of Constraints principles be
Q5: Table 7.12<br>A company desires to set up
Q6: The movement of product from one station
Q7: Table 7.12<br>A company desires to set up
Q12: Table 7.7<br>A company makes four products that
Q13: The process batch at the constraint in
Q13: Table 7.4 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 7.4
Q92: A line balance that is 100% efficient