Multiple Choice
Table 2.4
-Using Table 2.4,what is the earliest completion time for this project?
A) 18 weeks
B) 19 weeks
C) 20 weeks
D) 21 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Figure to accompany Table 2.9 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q13: Table 2.8<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.8
Q14: Table 2.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.7
Q15: Table 2.15<br>You are responsible for managing a
Q18: Table 2.8<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.8
Q20: Table 2.15<br>You are responsible for managing a
Q22: Table 2.6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.6
Q51: The normal cost is the amount of
Q78: The _ is the shortest time in
Q91: When using the beta distribution for estimating