Multiple Choice
Table 2.11
-Using Table 2.11 and assuming all activities except D,F,H,and K are available to be crashed,what is the minimum cost to be incurred in reducing the total project earliest completion time by one week?
A) $3,000
B) $6,000
C) $8,000
D) $10,000
Correct Answer:

Verified
Correct Answer:
Verified