Multiple Choice
Table 2.13
(All activity times for the project are in weeks. )
-Using Table 2.13,what is the critical path of this project?
A) A-C-F-H
B) B-D-F-H
C) B-D-G
D) B-E-G
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Table 2.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.7
Q2: Table 2.5 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.5
Q5: Figure to accompany Table 2.9 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q6: Table 2.6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Table 2.6
Q7: A project organization structure where team members
Q8: Figure to accompany Table 2.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q9: Figure to accompany Table 2.9 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg"
Q10: Fig.2.1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2904/.jpg" alt="Fig.2.1 -For
Q27: A critical path is any sequence of
Q87: Which of these is NOT one of