You are responsible for managing a project with the following activities (times are given in weeks) . Table 2.14 You are responsible for managing a project with the following activities (times are given in weeks) .   -Using Table 2.14,which activity has the largest slack,and how large is that slack? A) Activity C;five weeks B) Activity A;six weeks C) Activity B;four weeks D) Activity E;three weeks
-Using Table 2.14,which activity has the largest slack,and how large is that slack?


A) Activity C;five weeks
B) Activity A;six weeks
C) Activity B;four weeks
D) Activity E;three weeks