Multiple Choice
Table 2.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 2.14,which activity has the largest slack,and how large is that slack?
A) Activity C;five weeks
B) Activity A;six weeks
C) Activity B;four weeks
D) Activity E;three weeks
Correct Answer:

Verified
Correct Answer:
Verified