    The Standard Time for a Work Element Is Found by Multiplying
Solved

The Standard Time for a Work Element Is Found by Multiplying

Question 75

Question 75

True/False

The standard time for a work element is found by multiplying the select time by a performance rating factor.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q70: The predetermined data approach does not eliminate

Q71: Special training is required for observers using

Q72: When using work sampling, the times of

Q73: A work sampling method is used to

Q74: With a time study approach, the:<br>A) nature

Q76: A larger sample size is required when

Q77: The most commonly used method for setting

Q78: The methods time measurement system is a

Q79: Why is a sampling schedule important in

Q80: A time study is the method most

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines