Keith assembles peanut valves and the recorded data is displayed in the table.What is the select time for this job element?
A) greater than or equal to 3 minutes
B) less than 3 minutes but greater than or equal to 2.7 minutes
C) less than 2.7 minutes but greater than or equal to 2.4 minutes
D) less than 2.4 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q5: An undergraduate business student studies diligently in
Q12: A larger sample size is required when
Q13: A pilot work study has been conducted
Q15: Table H.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table H.2
Q27: The process of creating labor standards based
Q29: A time study analyst is attempting to
Q49: The more frequently the activity occurs, the
Q62: Table H.2<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table H.2
Q65: An analyst divides each work element into
Q93: When using a time study approach, the