Multiple Choice
At a new watch assembly plant,a job is divided into three work elements.The element times for the first four cycles are recorded by the continuous method and are presented below along with a performance rating factor (RF) for each element. The standard time for this job,assuming that the allowance is 18 percent,is:
A) fewer than or equal to 1.9 minutes.
B) greater than 1.9 minutes but fewer than or equal to 2.0 minutes.
C) greater than 2.0 minutes but fewer than or equal to 2.1 minutes.
D) greater than 2.1 minutes.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: The performance rating factor in a time
Q23: A time study analysis was performed on
Q26: Table H.1<br>A worker was observed for four
Q42: The sample size needed for a time
Q43: The gentleman farmer recorded the time it
Q44: The gentleman farmer recorded the time it
Q46: What are the limitations of time studies?
Q48: A work sampling method is used to
Q49: Which one of the following statements about
Q106: A time study analyst has found the