A double-sampling plan has n1 = 50,n2 = 100,c1 = 2,and c2 = 4.Suppose the first sample revealed two defectives.What should be done?
A) Reject the entire lot.
B) Take a second sampling of 100 units.
C) Accept the entire lot.
D) Repeat the tests on the first sample.