Essay
Consider the MPS,BOM,and inventory data shown.
Master Production Schedule:
The following table shows the MPS start quantities for the next 10 weeks.
Bill of Material:
- Item A uses 2 each of component D,1 each of component C and 2 each of subassembly B.
- Subassembly B uses 2 each of component E.
Selected Inventory Data:
Construct the MRP schedule using the preceding information.Blank MRP records are provided at the end of this test.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Explain why, in a dependent demand environment,
Q12: Scenario 11.2 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1253/.jpg" alt="Scenario 11.2
Q14: Scenario 11.3<br>Use this bill of materials and
Q16: Which of the following statements about MRP
Q19: Use the following partially completed MRP record
Q51: A parent is any item manufactured from
Q82: A front-office module for an ERP system
Q94: Operations produces a number of items in
Q116: If the demand for an independent demand
Q122: Lot-for-lot (L4L) is a rule that maintains