Multiple Choice
Table 10.4
Gable Express Co. provides delivery service seven days a week. The daily requirements (in workers) are estimated as follows:
Each worker is required to work five days per week, and each must have two consecutive days off.
-Use the information in Table 10.4. How much total slack will be generated from the schedule?
A) fewer than six days
B) six days
C) seven days
D) greater than seven days
Correct Answer:

Verified
Correct Answer:
Verified