The daily requirements for highway patrol officers at Park City over the week are:
Each officer works five days a week and must have two consecutive days off.
-Use the information in Table 10.5. How much total slack is generated from the schedule?
A) fewer than 9 days
B) 10 days
C) 11 days
D) greater than 11 days