Essay
Use the information in the preceding table and sequence the six jobs using FCFS and EDD.The jobs are listed in the order of their arrival.Calculate the average flow time and average past due.It is now time zero.
Correct Answer:

Verified
Average Flow Time = 159 ÷ 6 =...View Answer