Use the Information in the Preceding Table and Sequence the Seven

Question 121

Essay

  Use the information in the preceding table and sequence the seven jobs using first come,first served (FCFS)and earliest due date (EDD).Calculate the average flow time and average past due.It is now time 5. Use the information in the preceding table and sequence the seven jobs using first come,first served (FCFS)and earliest due date (EDD).Calculate the average flow time and average past due.It is now time 5.

Correct Answer:

verifed

Verified

The FCFS sequence is:
blured image Averag...