Multiple Choice
Assume that activity G has the following times: Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is TRUE about activity G?
A) Activity G takes 14 days to complete.
B) Activity G has a slack time of 8 days.
C) Activity G is on the critical path.
D) Activity G takes 2 days to complete.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q13: Phoebe B.Beebee is constructing a canal for
Q15: The following table contains a list of
Q34: Table 7.8<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.8
Q55: Risk is a measure of the probability
Q83: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q117: Projects, and the application of project management,
Q132: Table 7.14<br>You are responsible for managing a
Q133: A good risk management plan will contain
Q137: Table 7.6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.6