Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, what is the critical path and expected completion time for this project?
A) D-E; 29.5 weeks
B) A-B-C; 25 weeks
C) D-E; 27.5 weeks
D) A-B-C; 26.5 weeks
Correct Answer:

Verified
Correct Answer:
Verified
Q127: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q128: The savvy project manager knew there would
Q129: A project has three paths. A-B-C has
Q130: Table 7.9<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.9
Q131: Figure to accompany Table 7.7<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q133: A good risk management plan will contain
Q134: Table 7.4<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.4
Q135: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5
Q136: In making an estimate of the most
Q137: Table 7.6<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.6