Essay
Consider the activities,durations,and predecessor relationships in the following network.Draw the network and answer the questions that follow.
a.What is the expected time for activity B?
b.What is the variance for activity B?
c.Based on the calculation of estimated times,what is the critical path?
d.What is the estimated time of the critical path?
e.What is the activity variance along the critical path?
f.What is the probability of completion of the project before week 42?
Correct Answer:

Verified
a.
=
= 9 weeks
b.
=
=
= 9.00
c.A-C...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
b.
c.A-C...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q5: The _ is determined by starting with
Q13: Phoebe B.Beebee is constructing a canal for
Q15: The following table contains a list of
Q28: A project manager hires a few new
Q66: In addition to finishing the work, the
Q77: Table 7.13<br>All activity times for the project
Q83: Figure to accompany Table 7.1<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg"
Q97: Describe how time-cost tradeoffs for project activities
Q117: Projects, and the application of project management,
Q135: Table 7.5<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 7.5