Multiple Choice
A manufacturer embarking on a Six Sigma program sets the goal of having true Six Sigma capability for all processes by the end of the month.If their current process capability index on a key metric is less than 2.0 and the process capability ratio is 1.5,what must happen with the process standard deviation?
A) The process standard deviation must be reduced by 25%.
B) The process standard deviation must be reduced by 33%.
C) The process standard deviation must be reduced by 50%.
D) The process standard deviation must be reduced by 67%.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Improving quality seems to be a strategic
Q16: Samples of size four were taken from
Q18: One of the principles that total quality
Q42: The underlying statistical distribution for the p-chart
Q57: The three sigma limits for a process
Q59: The Baldrige Performance Excellence Program:<br>A) focuses on
Q111: The defect rate for a product has
Q124: Table 5.3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB1252/.jpg" alt="Table 5.3
Q154: _ of variation include any variation-causing factors
Q185: In acceptance sampling, when the random sample