Multiple Choice
A manager is trying to estimate the appropriate learning curve for a certain job. The manager notes that the first four units had a total time of 30 minutes. Which learning curve would yield approximately this result if the first unit took 9 minutes? (Use Table E.3 (in the text) cumulative coefficient.)
A) 0.70
B) 0.75
C) 0.80
D) 0.85
E) 0.90
Correct Answer:

Verified
Correct Answer:
Verified