Essay
A work cell is scheduled to build 120 digital light processor (DLP) assemblies each week. These assemblies are later installed into home theatre projection systems. The work cell has 7.5 hours of productive work each day, six days per week. What is takt time for this cell?
Correct Answer:

Verified
The cell has 7.5 × 6 = 45 hour...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q58: Category management is the use of computer
Q64: An assembly line consists of 21 tasks
Q65: The fixed-position layout would be most appropriate
Q68: A facility is trying to set
Q72: There are three work centers (A,
Q73: Cycle time is computed as:<br>A) desired output
Q131: Balancing a work cell is done:<br>A)before the
Q148: In a product-oriented layout, the process of
Q214: Ambient conditions; spatial layout and functionality; and
Q317: The biggest advantage of a product layout