Multiple Choice
The critical path for the network activities shown below is ________ with duration ________.
A) A-B-D;10
B) A-B-E;11
C) C-E;12
D) A-D-E;13
E) A-B-C-D-E;22
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q5: Which of the following statements regarding PERT
Q20: A project being analyzed by PERT has
Q27: The PERT pessimistic time estimate is an
Q35: Which of the following statements regarding PERT
Q50: Slack is the amount of time an
Q63: An activity on a PERT network has
Q65: Define slack.
Q87: What are the earliest activity start time
Q113: _ is the amount of time an
Q115: Which of the following statements regarding time-cost