When Deciding Among Mutually Exclusive Projects, a Public Manager Should

Question 14

Multiple Choice

When deciding among mutually exclusive projects, a public manager should choose:


A) all projects that have benefit-cost ratios greater than one.
B) all the projects that have positive net benefits.
C) the project with the greatest benefit-cost ratio.
D) the project with the greatest positive net benefit.
E) the project with the lowest total cost.