Deck 12: Project Management
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/85
Play
Full screen (f)
Deck 12: Project Management
1
A Gantt chart provides a visual display of the project schedule that includes scheduled start times,finish times and available slack.
True
2
The three major components of project management include planning,scheduling,and costing.
False
3
Two key elements of project control are time management and cost management.
True
4
Managing quality is not an important part of project management.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
5
In general,projects are subject to less uncertainty than other types of processes.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
6
A unique,one-time operational activity or effort is referred to as a process.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
7
The upper level of a work breakdown structure for a project highlights summary activities and/or major components.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
8
Slack represents the amount of time an activity can be delayed without delaying the project completion time.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
9
Management and control of a companywide portfolio of projects is known as enterprise project management.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
10
The principles of total quality management (TQM)cannot be applied to project management.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
11
Project scope involves a set of procedures for anticipating and assessing uncertainties that might increase the risk of delaying the project.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
12
Enterprise project management refers to the management and control of a large,complex project.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
13
Project control involves monitoring a project and measuring its progress toward a successful completion.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
14
A project team is typically cross-functional consisting of members throughout an organization.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
15
PERT stands for program enterprise and resource technique.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
16
Earned value analysis reports a project's performance by tracking its forecasted completion date and anticipated budget variations.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
17
A work breakdown structure provides a common understanding of and justification for a project.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
18
Project planning involves a set of procedures for monitoring and evaluating progress and performance.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
19
With an activity-on-node (AON)network diagram,the nodes indicate the precedence relationships and the arrows represent the project's activities.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
20
Project scheduling is recognized as the most critical element in the project management process.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
21
Microsoft Project is a software package that supports PERT but not CPM.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
22
Issues of cultural diversity in project management should only be addressed if and when they arise.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
23
Unlike PERT,CPM incorporates probabilistic time estimates into the project management process.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
24
A(n)___ is a project team structure that includes members from different functional areas.
A)matrix organization
B)project network
C)organizational breakdown structure
D)work breakdown structure
A)matrix organization
B)project network
C)organizational breakdown structure
D)work breakdown structure
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
25
The project management process encompasses
A)planning.
B)scheduling.
C)control.
D)all of the above.
A)planning.
B)scheduling.
C)control.
D)all of the above.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
26
A project's duration can be reduced by crashing activities on the critical path.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
27
Crashing activates with positive slack reduces a project's duration.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
28
A dummy activity is an activity inserted into the network diagram to show a precedence relationship,but does not represent any passage of time.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
29
A ___ breaks down a project into components,subcomponents,activities,and tasks.
A)work breakdown structure (WBS)
B)scope statement
C)responsibility assignment matrix (RAM)
D)organizational breakdown structure (OBS)
A)work breakdown structure (WBS)
B)scope statement
C)responsibility assignment matrix (RAM)
D)organizational breakdown structure (OBS)
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
30
The earliest start time for an activity is at time zero.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
31
Activities that are not on a project's critical path have zero slack.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
32
Which of the following is not a general characteristic of a project?
A)A project has a unique purpose.
B)A project has more certainty.
C)A project has more uncertainty.
D)A project often draws resources from various areas in the organization.
A)A project has a unique purpose.
B)A project has more certainty.
C)A project has more uncertainty.
D)A project often draws resources from various areas in the organization.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
33
In general,crashing costs decrease as a project's duration is shortened.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
34
Because the critical path is the shortest path through a network it defines the minimum project completion time.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
35
Indirect costs always increase as a project's duration decreases.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
36
Asian cultures tend to embrace project management's methodical approach more than western cultures.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
37
Global projects rarely are concerned with cultural differences among team members because English is the universal business language.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
38
Which of the following is not a basic element in a project plan?
A)objectives
B)personnel
C)contract requirements
D)All the above are basic elements.
A)objectives
B)personnel
C)contract requirements
D)All the above are basic elements.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
39
The critical path is the shortest path through the project's network.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
40
The ___ is a document that provides a common understanding,justification,and expected result for a project.
A)statement of work
B)work breakdown structure
C)scope statement.
D)responsibility assignment matrix
A)statement of work
B)work breakdown structure
C)scope statement.
D)responsibility assignment matrix
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
41
The longest path through a project network is referred to as the
A)activity-on-node path.
B)path of greatest slack.
C)critical path.
D)noncritical path.
A)activity-on-node path.
B)path of greatest slack.
C)critical path.
D)noncritical path.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
42
In general,the latest finish time for an activity is equal to
A)latest finish time minus the activity time estimate.
B)the minimum of the latest start times for the activities that immediately follow.
C)the maximum of the latest start times for the activities that immediately follow.
D)the average of the latest start times for the activities that immediately follow.
A)latest finish time minus the activity time estimate.
B)the minimum of the latest start times for the activities that immediately follow.
C)the maximum of the latest start times for the activities that immediately follow.
D)the average of the latest start times for the activities that immediately follow.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
43
The slack time for an activity can be computed as
A)latest start time (LS)- latest finish time (LF).
B)earliest start time (ES)+ earliest finish time (EF).
C)latest start time (LS)- earliest start time (ES).
D)latest finish time (LF)+ earliest finish time (EF).
A)latest start time (LS)- latest finish time (LF).
B)earliest start time (ES)+ earliest finish time (EF).
C)latest start time (LS)- earliest start time (ES).
D)latest finish time (LF)+ earliest finish time (EF).
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
44
A project consists of the following activities: Table 9.1
Using Table 9.1,the earliest finish (EF)time for activity D is
A)7 weeks.
B)13 weeks.
C)20 weeks.
D)30 weeks.

A)7 weeks.
B)13 weeks.
C)20 weeks.
D)30 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
45
Using Table 9.1,the latest start (LS)time for activity B is
A)5 weeks.
B)8 weeks.
C)13 weeks.
D)14 weeks.
A)5 weeks.
B)8 weeks.
C)13 weeks.
D)14 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
46
For activities on a project's critical path
A)earliest start time (ES)equals latest start time (LS).
B)earliest start time (ES)is greater than latest start time (LS).
C)earliest start time (ES)is less than latest start time (LS).
D)earliest start time (ES)equals latest finish time (LF).
A)earliest start time (ES)equals latest start time (LS).
B)earliest start time (ES)is greater than latest start time (LS).
C)earliest start time (ES)is less than latest start time (LS).
D)earliest start time (ES)equals latest finish time (LF).
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
47
In project management,the term slack refers to the amount of time
A)to complete an activity without delaying the project.
B)an activity can be delayed without delaying the project.
C)needed to complete the entire project.
D)required to complete the project's critical activities.
A)to complete an activity without delaying the project.
B)an activity can be delayed without delaying the project.
C)needed to complete the entire project.
D)required to complete the project's critical activities.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
48
The ___ probability distribution is typically used to describe uncertain activity times in a project.
A)beta
B)normal
C)binomial
D)exponential
A)beta
B)normal
C)binomial
D)exponential
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
49
The key elements of project control includes all the following except
A)time management.
B)cost management.
C)material management.
D)communication.
A)time management.
B)cost management.
C)material management.
D)communication.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
50
The estimated variance for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days,and the pessimistic time (b)equal to 18 days is
A)2 days.
B)4 days.
C)6 days.
D)11 days.
A)2 days.
B)4 days.
C)6 days.
D)11 days.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
51
One disadvantage of a Gantt chart,especially for large projects,is that it does not
A)clearly show precedence relationships.
B)indicate activity start times.
C)indicate activity finish times.
D)use bars to represent activities.
A)clearly show precedence relationships.
B)indicate activity start times.
C)indicate activity finish times.
D)use bars to represent activities.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
52
For an activity-on-node (AON)network
A)arrows represent activities and nodes represent events.
B)nodes represent activities and arrows indicate precedence relationships.
C)arrows represent events and nodes indicate precedence relationships.
D)nodes indicate precedence relationships and arrows indicates the length of the activity time.
A)arrows represent activities and nodes represent events.
B)nodes represent activities and arrows indicate precedence relationships.
C)arrows represent events and nodes indicate precedence relationships.
D)nodes indicate precedence relationships and arrows indicates the length of the activity time.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
53
The estimated mean time for an activity with a most likely time (m)equal to 11 days,the optimistic time (a)equal to 6 days,and the pessimistic time (b)equal to 18 days is
A)9.67 days.
B)11 days.
C)11.33 days.
D)11.67 days.
A)9.67 days.
B)11 days.
C)11.33 days.
D)11.67 days.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
54
Using Table 9.1,the earliest start time for activity F is
A)30 weeks.
B)20 weeks.
C)14 weeks.
D)13 weeks.
A)30 weeks.
B)20 weeks.
C)14 weeks.
D)13 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
55
The estimated mean time for an activity with a most likely time (m)equal to 12 weeks,an optimistic time (a)equal to 9 weeks,and a pessimistic time (b)equal to 18 weeks is
A)13.0 weeks.
B)12.75 weeks.
C)12.5 weeks.
D)9.0 weeks.
A)13.0 weeks.
B)12.75 weeks.
C)12.5 weeks.
D)9.0 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
56
The estimated variance for an activity with a most likely time (m)equal to 12 weeks,an optimistic time (a)equal to 9 weeks,and a pessimistic time (b)equal to 18 weeks is
A)3.75 weeks.
B)1.50 weeks.
C)5.25 weeks.
D)2.25 weeks.
A)3.75 weeks.
B)1.50 weeks.
C)5.25 weeks.
D)2.25 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
57
Which of the following is not used to calculate probabilistic time estimates?
A)optimistic
B)most likely
C)least likely
D)pessimistic
A)optimistic
B)most likely
C)least likely
D)pessimistic
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
58
A standard procedure for numerically measuring a project's progress is referred to as a(n)
A)program evaluation and review technique (PERT).
B)critical path method (CPM).
C)Gantt chart.
D)earned value analysis.
A)program evaluation and review technique (PERT).
B)critical path method (CPM).
C)Gantt chart.
D)earned value analysis.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
59
In general,the earliest finish time for an activity is equal to
A)earliest start time + activity time estimate.
B)earliest start time - activity time estimate.
C)earliest start time - slack time.
D)earliest start time + slack time.
A)earliest start time + activity time estimate.
B)earliest start time - activity time estimate.
C)earliest start time - slack time.
D)earliest start time + slack time.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
60
A bar graph displaying when activities are scheduled to start,when they will be finished,and where extra time is available is known as a
A)PERT chart.
B)work breakdown structure (WBS).
C)Gantt chart.
D)responsibility assignment matrix (RAM).
A)PERT chart.
B)work breakdown structure (WBS).
C)Gantt chart.
D)responsibility assignment matrix (RAM).
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
61
The following table of probabilistic time estimates (in weeks)and activity predecessors are provided for a project. Table 9.2
Using Table 9.2,the expected time to complete activity A is
A)5.00 weeks.
B)7.33 weeks.
C)7.67 weeks.
D)8.00 weeks.

A)5.00 weeks.
B)7.33 weeks.
C)7.67 weeks.
D)8.00 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
62
Using Table 9.2,the expected time to complete the project is
A)34.17 weeks.
B)33.23 weeks.
C)31.00 weeks.
D)21.67 weeks.
A)34.17 weeks.
B)33.23 weeks.
C)31.00 weeks.
D)21.67 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
63
Using Table 9.3,the amount of slack associated with activity C is
A)4 days.
B)3 days.
C)2 days.
D)1 day.
A)4 days.
B)3 days.
C)2 days.
D)1 day.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
64
Using Table 9.3,the critical path for this project is
A)A-B-C.
B)A-C-D.
C)A-B-D.
D)A-B-C-D.
A)A-B-C.
B)A-C-D.
C)A-B-D.
D)A-B-C-D.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
65
Using Table 9.3,the latest start (LS)time for activity D is
A)8 days.
B)11 days.
C)19 days.
D)12 days.
A)8 days.
B)11 days.
C)19 days.
D)12 days.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
66
Which of the following statements is generally true regarding the relationship between project crashing costs and indirect costs?
A)Both crashing costs and indirect costs are highest when the project is shortened.
B)Only indirect costs increase when the project is shortened.
C)Both are unaffected by the length of the project.
D)Crashing costs increase when the project is shortened while indirect costs decrease when the project is shortened.
A)Both crashing costs and indirect costs are highest when the project is shortened.
B)Only indirect costs increase when the project is shortened.
C)Both are unaffected by the length of the project.
D)Crashing costs increase when the project is shortened while indirect costs decrease when the project is shortened.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
67
Using Table 9.2,the critical path for the project consists of activities
A)A-B-C-D-E.
B)A-B-C-E.
C)A-B-D-E.
D)A-B-C-D.
A)A-B-C-D-E.
B)A-B-C-E.
C)A-B-D-E.
D)A-B-C-D.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
68
Using Table 9.2,the probability that the project could be completed in 34 weeks or less is approximately
A)0.86.
B)0.89.
C)0.91.
D)0.96.
A)0.86.
B)0.89.
C)0.91.
D)0.96.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
69
Using Table 9.3,the time to complete the entire project would be
A)23 days.
B)19 days.
C)17 days.
D)11 days.
A)23 days.
B)19 days.
C)17 days.
D)11 days.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
70
Using Table 9.2,how much slack is associated with activity C?
A)0 weeks.
B)4.50 weeks.
C)12.67 weeks.
D)31.00 weeks.
A)0 weeks.
B)4.50 weeks.
C)12.67 weeks.
D)31.00 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
71
Using Table 9.1,the amount of slack associated with activity C is
A)0 weeks.
B)3 weeks.
C)6 weeks.
D)cannot be calculated.
A)0 weeks.
B)3 weeks.
C)6 weeks.
D)cannot be calculated.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
72
Using Table 9.2,the variance of the project's total completion time is
A)5.472.
B)5.222.
C)4.872.
D)3.752.
A)5.472.
B)5.222.
C)4.872.
D)3.752.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
73
Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately
A)0.19.
B)0.32.
C)0.68.
D)0.81.
A)0.19.
B)0.32.
C)0.68.
D)0.81.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
74
Using Table 9.1,the time complete the entire project is
A)20 weeks.
B)30 weeks.
C)36 weeks.
D)39 weeks.
A)20 weeks.
B)30 weeks.
C)36 weeks.
D)39 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
75
Using Table 9.2,the variance for activity E is
A)1.291.
B)1.667.
C)2.582.
D)2.778.
A)1.291.
B)1.667.
C)2.582.
D)2.778.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
76
Using Table 9.1,the critical path for this project consists of activities
A)A-B-C-D-E-F.
B)A-C-E-F.
C)A-B-C-F.
D)A-B-D-F.
A)A-B-C-D-E-F.
B)A-C-E-F.
C)A-B-C-F.
D)A-B-D-F.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
77
Using Table 9.2,the earliest finish time for activity C is
A)5.00 weeks.
B)8.17 weeks.
C)9.50 weeks.
D)12.67 weeks.
A)5.00 weeks.
B)8.17 weeks.
C)9.50 weeks.
D)12.67 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
78
A project consists of the following four activities with activity times in days: Table 9.3
Using Table 9.3,the earliest finish (EF)time for activity C is
A)4 days.
B)6 days.
C)10 days.
D)11 days.

A)4 days.
B)6 days.
C)10 days.
D)11 days.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
79
Using Table 9.3,the earliest start (ES)time for activity B is
A)5 days.
B)6 days.
C)11 days.
D)14 days.
A)5 days.
B)6 days.
C)11 days.
D)14 days.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck
80
Using Table 9.2,the earliest start (ES)time for activity D is
A)8.17 weeks.
B)12.67 weeks.
C)18.33 weeks.
D)21.67 weeks.
A)8.17 weeks.
B)12.67 weeks.
C)18.33 weeks.
D)21.67 weeks.
Unlock Deck
Unlock for access to all 85 flashcards in this deck.
Unlock Deck
k this deck