Deck 7: Project Scheduling: Adding the Time Dimension

Full screen (f)
exit full mode
Question
A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions pessimistic) it will take 40 days, and if conditions are ideal optimistic), it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?

A) 18 days
B) 14 days
C) 6 days
D) 26.67 days
E) 42 days
Use Space or
up arrow
down arrow
to flip the card.
Question
Which of the following types of precedence relationships is/are especially useful in fast-tracking situations?

A) Start-to-start
B) Start-to-finish
C) Finish-to-start
D) Finish-to-finish
E) A & C only
F) None of the above
Question
Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.
<strong>Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.   13.   Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11? </strong> A) 100% B) 75% C) 50% D) 25% E) 10% <div style=padding-top: 35px>
13.
<strong>Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.   13.   Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11? </strong> A) 100% B) 75% C) 50% D) 25% E) 10% <div style=padding-top: 35px>
Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11?

A) 100%
B) 75%
C) 50%
D) 25%
E) 10%
Question
Which of the following schedule display formats can require the use of dummy activities?

A) Bar chart
B) AON diagram
C) Gantt chart
D) AOA diagram
E) None of the above - in fact, there is no such thing as a dummy activity
Question
The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value.
<strong>The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value.   Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation? </strong> A) 0% B) 25% C) 50% D) 75% E) 100% <div style=padding-top: 35px>
Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation?

A) 0%
B) 25%
C) 50%
D) 75%
E) 100%
Question
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project? </strong> A) 3 days B) 4 day C) 5 days D) 6 days E) 7 days <div style=padding-top: 35px>


-Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project?

A) 3 days
B) 4 day
C) 5 days
D) 6 days
E) 7 days
Question
The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
 Activity  Description  Predeces sor  Optimistic  Most Lik ely  Pessim istic  A  Digging 234 B  Replace line  A 11.52 C  Replace foot valve  B .511.5 D  Fill hole  C 1.525.5 E  Level soil  D .511.5 F  Reseed lawn  E .4.5.6\begin{array} { | c | l | c | c | c | c | } \hline \text { Activity } & \text { Description } & \text { Predeces sor } & \text { Optimistic } & \text { Most Lik ely } & \text { Pessim istic } \\\hline \text { A } & \text { Digging } & - & 2 & 3 & 4 \\\hline \text { B } & \text { Replace line } & \text { A } & 1 & 1.5 & 2 \\\hline \text { C } & \text { Replace foot valve } & \text { B } & .5 & 1 & 1.5 \\\hline \text { D } & \text { Fill hole } & \text { C } & 1.5 & 2 & 5.5 \\\hline \text { E } & \text { Level soil } & \text { D } & .5 & 1 & 1.5 \\\hline \text { F } & \text { Reseed lawn } & \text { E } & .4 & .5 & .6 \\\hline \end{array}


-If the plumber and his crew begin working at 7:00 a.m., what time are they expected to finish?

A) 3:00 p.m.
B) 3:30 p.m.
C) 4:00 p.m.
D) 4:30 p.m.
E) 5:00 p.m.
Question
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. Circle the letter of each activity that has free float. </strong> A) A B) B C) C D) D E) E F) F G) G <div style=padding-top: 35px>


-Assume all activities are scheduled to begin on their early start times. Circle the letter of each activity that has free float.

A) A
B) B
C) C
D) D
E) E
F) F
G) G
Question
Based on the table in the previous question showing time estimates for Activities A through E, which activity has a Standard Deviation of .833? Circle all that apply:

A) A
B) B
C) C
D) D
E) E
Question
The following software development plan is the basis for the next four questions
<strong>The following software development plan is the basis for the next four questions    -The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame? </strong> A) 54% B) 67% C) 75% D) 93% E) 100% <div style=padding-top: 35px>

-The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame?

A) 54%
B) 67%
C) 75%
D) 93%
E) 100%
Question
Which of the following is an example of a start-to-start relationship?

A) We cannot start design until five weeks after requirements definition is complete.
B) We cannot start pouring the concrete until the foundation has been completely excavated.
C) Editing cannot begin until two weeks after we have started writing the book.
D) The paving job cannot finish until we have started to put up the signs.
E) All of the above.
Question
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Which of these is the critical path for this project schedule? </strong> A) A-B-F-G B) A-B-D-G C) A-C-E-G D) ABCDEFG E) ABFDG <div style=padding-top: 35px>


-Which of these is the critical path for this project schedule?

A) A-B-F-G
B) A-B-D-G
C) A-C-E-G
D) ABCDEFG
E) ABFDG
Question
For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C. </strong> A) y = 4, z = 0 B) y = 0, z = 4 C) y = 0, z = 0 D) y = 4, z = 4 E) None of the above <div style=padding-top: 35px>
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C. </strong> A) y = 4, z = 0 B) y = 0, z = 4 C) y = 0, z = 0 D) y = 4, z = 4 E) None of the above <div style=padding-top: 35px>


-Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C.

A) y = 4, z = 0
B) y = 0, z = 4
C) y = 0, z = 0
D) y = 4, z = 4
E) None of the above
Question
Which of the following is NOT a characteristic of the PERT method?

A) It assumes project activities are independent of each other and not affected by common factors.
B) Total project time TE)) is assumed to have a normal distribution.
C) The distribution of possible times for an individual activity is described as a beta distribution.
D) Activity estimates are known and certain.
E) All of the above are characteristics of the PERT method.
Question
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have? </strong> A) 0 days B) 1 day C) 2 days D) 3 days E) 4 days F) 5 days <div style=padding-top: 35px>


-Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have?

A) 0 days
B) 1 day
C) 2 days
D) 3 days
E) 4 days
F) 5 days
Question
The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
 Activity  Description  Predeces sor  Optimistic  Most Lik ely  Pessim istic  A  Digging 234 B  Replace line  A 11.52 C  Replace foot valve  B .511.5 D  Fill hole  C 1.525.5 E  Level soil  D .511.5 F  Reseed lawn  E .4.5.6\begin{array} { | c | l | c | c | c | c | } \hline \text { Activity } & \text { Description } & \text { Predeces sor } & \text { Optimistic } & \text { Most Lik ely } & \text { Pessim istic } \\\hline \text { A } & \text { Digging } & - & 2 & 3 & 4 \\\hline \text { B } & \text { Replace line } & \text { A } & 1 & 1.5 & 2 \\\hline \text { C } & \text { Replace foot valve } & \text { B } & .5 & 1 & 1.5 \\\hline \text { D } & \text { Fill hole } & \text { C } & 1.5 & 2 & 5.5 \\\hline \text { E } & \text { Level soil } & \text { D } & .5 & 1 & 1.5 \\\hline \text { F } & \text { Reseed lawn } & \text { E } & .4 & .5 & .6 \\\hline \end{array}


-Carol Spalding can't bear to see her lawn all dug up so she has decided to visit her mother on the day the work is to be done. Carol wants to return home at 6:45 p.m., what is the probability the work will be complete when Carol arrives home?

A) 95%
B) 99.3%
C) 99.5%
D) 99.8%
E) 100%
Question
The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
 Activity  Description  Predeces sor  Optimistic  Most Lik ely  Pessim istic  A  Digging 234 B  Replace line  A 11.52 C  Replace foot valve  B .511.5 D  Fill hole  C 1.525.5 E  Level soil  D .511.5 F  Reseed lawn  E .4.5.6\begin{array} { | c | l | c | c | c | c | } \hline \text { Activity } & \text { Description } & \text { Predeces sor } & \text { Optimistic } & \text { Most Lik ely } & \text { Pessim istic } \\\hline \text { A } & \text { Digging } & - & 2 & 3 & 4 \\\hline \text { B } & \text { Replace line } & \text { A } & 1 & 1.5 & 2 \\\hline \text { C } & \text { Replace foot valve } & \text { B } & .5 & 1 & 1.5 \\\hline \text { D } & \text { Fill hole } & \text { C } & 1.5 & 2 & 5.5 \\\hline \text { E } & \text { Level soil } & \text { D } & .5 & 1 & 1.5 \\\hline \text { F } & \text { Reseed lawn } & \text { E } & .4 & .5 & .6 \\\hline \end{array}


-The plumber has scheduled another small job at 6:00 p.m. If it takes 1/2 hour to drive from the Spalding's to the other job, what is the probability the plumber will be able to make the 6:00 p.m. appointment on time?

A) 63%
B) 75%
C) 89%
D) 95%
E) 99%
Question
For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D. </strong> A) w = 2, x = 6 B) w = 4, x = 8 C) w = 5, x = 9 D) w = 6, x = 10 E) None of the above <div style=padding-top: 35px>
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D. </strong> A) w = 2, x = 6 B) w = 4, x = 8 C) w = 5, x = 9 D) w = 6, x = 10 E) None of the above <div style=padding-top: 35px>


-Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D.

A) w = 2, x = 6
B) w = 4, x = 8
C) w = 5, x = 9
D) w = 6, x = 10
E) None of the above
Question
The following software development plan is the basis for the next four questions
<strong>The following software development plan is the basis for the next four questions    -The client has asked for an estimated completion date. What would you tell her?</strong> A) 35 weeks B) 41 weeks C) 28 weeks D) 21 weeks E) none of the above <div style=padding-top: 35px>

-The client has asked for an estimated completion date. What would you tell her?

A) 35 weeks
B) 41 weeks
C) 28 weeks
D) 21 weeks
E) none of the above
Question
The table below shows PERT estimates te) for activities A through E.
 Time estimates (days) \text { Time estimates (days) }
 Activity t(o)t(m)t(p)t(e)A459?B137?C3610?D2812?E146?\begin{array}{|c|c|c|c|c|}\hline \text { Activity }&t(o)&t(m)&t(p)&t(e)\\\hline \mathrm{A} & 4 & 5 & 9 & ? \\\hline \mathrm{B} & 1 & 3 & 7 & ? \\\hline \mathrm{C} & 3 & 6 & 10 & ? \\\hline \mathrm{D} & 2 & 8 & 12 & ? \\\hline \mathrm{E} & 1 & 4 & 6 & ? \\\hline\end{array}
Based on the table above, the te) for activities A, B and C are: .

A) 5 days, 3 days, 6 days
B) 5.500 days, 3.333 days, 6.167 days
C) 6 days, 3.667 days, 6.333 days
D) 3.167 days, 5.333 days, 1.833 days
E) 3 days, 1.667 days, 1.833 days
F) None of the above
Question
The following software development plan is the basis for the next four questions
<strong>The following software development plan is the basis for the next four questions    -The client has just asked if it would be possible to have the completed software in 36 weeks. What is the likelihood the project will be completed in that time frame?</strong> A) 54% B) 90% C) 100% D) 33% E) 63% <div style=padding-top: 35px>

-The client has just asked if it would be possible to have the completed software in 36 weeks. What is the likelihood the project will be completed in that time frame?

A) 54%
B) 90%
C) 100%
D) 33%
E) 63%
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/21
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 7: Project Scheduling: Adding the Time Dimension
1
A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions pessimistic) it will take 40 days, and if conditions are ideal optimistic), it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?

A) 18 days
B) 14 days
C) 6 days
D) 26.67 days
E) 42 days
14 days
2
Which of the following types of precedence relationships is/are especially useful in fast-tracking situations?

A) Start-to-start
B) Start-to-finish
C) Finish-to-start
D) Finish-to-finish
E) A & C only
F) None of the above
Start-to-start
3
Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.
<strong>Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.   13.   Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11? </strong> A) 100% B) 75% C) 50% D) 25% E) 10%
13.
<strong>Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.   13.   Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11? </strong> A) 100% B) 75% C) 50% D) 25% E) 10%
Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11?

A) 100%
B) 75%
C) 50%
D) 25%
E) 10%
25%
4
Which of the following schedule display formats can require the use of dummy activities?

A) Bar chart
B) AON diagram
C) Gantt chart
D) AOA diagram
E) None of the above - in fact, there is no such thing as a dummy activity
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
5
The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value.
<strong>The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value.   Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation? </strong> A) 0% B) 25% C) 50% D) 75% E) 100%
Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation?

A) 0%
B) 25%
C) 50%
D) 75%
E) 100%
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
6
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project? </strong> A) 3 days B) 4 day C) 5 days D) 6 days E) 7 days


-Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project?

A) 3 days
B) 4 day
C) 5 days
D) 6 days
E) 7 days
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
7
The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
 Activity  Description  Predeces sor  Optimistic  Most Lik ely  Pessim istic  A  Digging 234 B  Replace line  A 11.52 C  Replace foot valve  B .511.5 D  Fill hole  C 1.525.5 E  Level soil  D .511.5 F  Reseed lawn  E .4.5.6\begin{array} { | c | l | c | c | c | c | } \hline \text { Activity } & \text { Description } & \text { Predeces sor } & \text { Optimistic } & \text { Most Lik ely } & \text { Pessim istic } \\\hline \text { A } & \text { Digging } & - & 2 & 3 & 4 \\\hline \text { B } & \text { Replace line } & \text { A } & 1 & 1.5 & 2 \\\hline \text { C } & \text { Replace foot valve } & \text { B } & .5 & 1 & 1.5 \\\hline \text { D } & \text { Fill hole } & \text { C } & 1.5 & 2 & 5.5 \\\hline \text { E } & \text { Level soil } & \text { D } & .5 & 1 & 1.5 \\\hline \text { F } & \text { Reseed lawn } & \text { E } & .4 & .5 & .6 \\\hline \end{array}


-If the plumber and his crew begin working at 7:00 a.m., what time are they expected to finish?

A) 3:00 p.m.
B) 3:30 p.m.
C) 4:00 p.m.
D) 4:30 p.m.
E) 5:00 p.m.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
8
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. Circle the letter of each activity that has free float. </strong> A) A B) B C) C D) D E) E F) F G) G


-Assume all activities are scheduled to begin on their early start times. Circle the letter of each activity that has free float.

A) A
B) B
C) C
D) D
E) E
F) F
G) G
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
9
Based on the table in the previous question showing time estimates for Activities A through E, which activity has a Standard Deviation of .833? Circle all that apply:

A) A
B) B
C) C
D) D
E) E
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
10
The following software development plan is the basis for the next four questions
<strong>The following software development plan is the basis for the next four questions    -The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame? </strong> A) 54% B) 67% C) 75% D) 93% E) 100%

-The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame?

A) 54%
B) 67%
C) 75%
D) 93%
E) 100%
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following is an example of a start-to-start relationship?

A) We cannot start design until five weeks after requirements definition is complete.
B) We cannot start pouring the concrete until the foundation has been completely excavated.
C) Editing cannot begin until two weeks after we have started writing the book.
D) The paving job cannot finish until we have started to put up the signs.
E) All of the above.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
12
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Which of these is the critical path for this project schedule? </strong> A) A-B-F-G B) A-B-D-G C) A-C-E-G D) ABCDEFG E) ABFDG


-Which of these is the critical path for this project schedule?

A) A-B-F-G
B) A-B-D-G
C) A-C-E-G
D) ABCDEFG
E) ABFDG
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
13
For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C. </strong> A) y = 4, z = 0 B) y = 0, z = 4 C) y = 0, z = 0 D) y = 4, z = 4 E) None of the above
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C. </strong> A) y = 4, z = 0 B) y = 0, z = 4 C) y = 0, z = 0 D) y = 4, z = 4 E) None of the above


-Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C.

A) y = 4, z = 0
B) y = 0, z = 4
C) y = 0, z = 0
D) y = 4, z = 4
E) None of the above
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
14
Which of the following is NOT a characteristic of the PERT method?

A) It assumes project activities are independent of each other and not affected by common factors.
B) Total project time TE)) is assumed to have a normal distribution.
C) The distribution of possible times for an individual activity is described as a beta distribution.
D) Activity estimates are known and certain.
E) All of the above are characteristics of the PERT method.
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
15
The following network is the basis for the next four questions:
<strong>The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have? </strong> A) 0 days B) 1 day C) 2 days D) 3 days E) 4 days F) 5 days


-Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have?

A) 0 days
B) 1 day
C) 2 days
D) 3 days
E) 4 days
F) 5 days
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
16
The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
 Activity  Description  Predeces sor  Optimistic  Most Lik ely  Pessim istic  A  Digging 234 B  Replace line  A 11.52 C  Replace foot valve  B .511.5 D  Fill hole  C 1.525.5 E  Level soil  D .511.5 F  Reseed lawn  E .4.5.6\begin{array} { | c | l | c | c | c | c | } \hline \text { Activity } & \text { Description } & \text { Predeces sor } & \text { Optimistic } & \text { Most Lik ely } & \text { Pessim istic } \\\hline \text { A } & \text { Digging } & - & 2 & 3 & 4 \\\hline \text { B } & \text { Replace line } & \text { A } & 1 & 1.5 & 2 \\\hline \text { C } & \text { Replace foot valve } & \text { B } & .5 & 1 & 1.5 \\\hline \text { D } & \text { Fill hole } & \text { C } & 1.5 & 2 & 5.5 \\\hline \text { E } & \text { Level soil } & \text { D } & .5 & 1 & 1.5 \\\hline \text { F } & \text { Reseed lawn } & \text { E } & .4 & .5 & .6 \\\hline \end{array}


-Carol Spalding can't bear to see her lawn all dug up so she has decided to visit her mother on the day the work is to be done. Carol wants to return home at 6:45 p.m., what is the probability the work will be complete when Carol arrives home?

A) 95%
B) 99.3%
C) 99.5%
D) 99.8%
E) 100%
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
17
The following information is the basis for the next three questions.
Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required.
 Activity  Description  Predeces sor  Optimistic  Most Lik ely  Pessim istic  A  Digging 234 B  Replace line  A 11.52 C  Replace foot valve  B .511.5 D  Fill hole  C 1.525.5 E  Level soil  D .511.5 F  Reseed lawn  E .4.5.6\begin{array} { | c | l | c | c | c | c | } \hline \text { Activity } & \text { Description } & \text { Predeces sor } & \text { Optimistic } & \text { Most Lik ely } & \text { Pessim istic } \\\hline \text { A } & \text { Digging } & - & 2 & 3 & 4 \\\hline \text { B } & \text { Replace line } & \text { A } & 1 & 1.5 & 2 \\\hline \text { C } & \text { Replace foot valve } & \text { B } & .5 & 1 & 1.5 \\\hline \text { D } & \text { Fill hole } & \text { C } & 1.5 & 2 & 5.5 \\\hline \text { E } & \text { Level soil } & \text { D } & .5 & 1 & 1.5 \\\hline \text { F } & \text { Reseed lawn } & \text { E } & .4 & .5 & .6 \\\hline \end{array}


-The plumber has scheduled another small job at 6:00 p.m. If it takes 1/2 hour to drive from the Spalding's to the other job, what is the probability the plumber will be able to make the 6:00 p.m. appointment on time?

A) 63%
B) 75%
C) 89%
D) 95%
E) 99%
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
18
For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D. </strong> A) w = 2, x = 6 B) w = 4, x = 8 C) w = 5, x = 9 D) w = 6, x = 10 E) None of the above
<strong>For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:       -Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D. </strong> A) w = 2, x = 6 B) w = 4, x = 8 C) w = 5, x = 9 D) w = 6, x = 10 E) None of the above


-Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D.

A) w = 2, x = 6
B) w = 4, x = 8
C) w = 5, x = 9
D) w = 6, x = 10
E) None of the above
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
19
The following software development plan is the basis for the next four questions
<strong>The following software development plan is the basis for the next four questions    -The client has asked for an estimated completion date. What would you tell her?</strong> A) 35 weeks B) 41 weeks C) 28 weeks D) 21 weeks E) none of the above

-The client has asked for an estimated completion date. What would you tell her?

A) 35 weeks
B) 41 weeks
C) 28 weeks
D) 21 weeks
E) none of the above
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
20
The table below shows PERT estimates te) for activities A through E.
 Time estimates (days) \text { Time estimates (days) }
 Activity t(o)t(m)t(p)t(e)A459?B137?C3610?D2812?E146?\begin{array}{|c|c|c|c|c|}\hline \text { Activity }&t(o)&t(m)&t(p)&t(e)\\\hline \mathrm{A} & 4 & 5 & 9 & ? \\\hline \mathrm{B} & 1 & 3 & 7 & ? \\\hline \mathrm{C} & 3 & 6 & 10 & ? \\\hline \mathrm{D} & 2 & 8 & 12 & ? \\\hline \mathrm{E} & 1 & 4 & 6 & ? \\\hline\end{array}
Based on the table above, the te) for activities A, B and C are: .

A) 5 days, 3 days, 6 days
B) 5.500 days, 3.333 days, 6.167 days
C) 6 days, 3.667 days, 6.333 days
D) 3.167 days, 5.333 days, 1.833 days
E) 3 days, 1.667 days, 1.833 days
F) None of the above
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
21
The following software development plan is the basis for the next four questions
<strong>The following software development plan is the basis for the next four questions    -The client has just asked if it would be possible to have the completed software in 36 weeks. What is the likelihood the project will be completed in that time frame?</strong> A) 54% B) 90% C) 100% D) 33% E) 63%

-The client has just asked if it would be possible to have the completed software in 36 weeks. What is the likelihood the project will be completed in that time frame?

A) 54%
B) 90%
C) 100%
D) 33%
E) 63%
Unlock Deck
Unlock for access to all 21 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 21 flashcards in this deck.