Exam 7: Project Scheduling: Adding the Time Dimension

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

The following software development plan is the basis for the next four questions The following software development plan is the basis for the next four questions   -The client has asked for an estimated completion date. What would you tell her? -The client has asked for an estimated completion date. What would you tell her?

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
Verified

A

The following information is the basis for the next three questions. Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required. Activity Description Predeces sor Optimistic Most Lik ely Pessim istic A Digging - 2 3 4 B Replace line A 1 1.5 2 C Replace foot valve B .5 1 1.5 D Fill hole C 1.5 2 5.5 E Level soil D .5 1 1.5 F Reseed lawn E .4 .5 .6 -The plumber has scheduled another small job at 6:00 p.m. If it takes 1/2 hour to drive from the Spalding's to the other job, what is the probability the plumber will be able to make the 6:00 p.m. appointment on time?

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
Verified

C

Based on the table in the previous question showing time estimates for Activities A through E, which activity has a Standard Deviation of .833? Circle all that apply:

Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
Verified

A , E

Which of the following is an example of a start-to-start relationship?

(Multiple Choice)
4.7/5
(36)

Which of the following types of precedence relationships is/are especially useful in fast-tracking situations?

(Multiple Choice)
4.9/5
(31)

The following network is the basis for the next four questions: The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project? -Assume all activities are scheduled to begin on their early start times. How much can we delay activity D without delaying the project?

(Multiple Choice)
4.8/5
(30)

For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity: For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:      -Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D. -Calculate the LS late start) and LF late finish) values - indicated by w and x - for Task D.

(Multiple Choice)
4.9/5
(38)

A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions pessimistic) it will take 40 days, and if conditions are ideal optimistic), it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?

(Multiple Choice)
4.8/5
(36)

Which of the following is NOT a characteristic of the PERT method?

(Multiple Choice)
4.8/5
(29)

For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity: For the next two questions, refer to the following AON diagram, with ES, LS, EF, LF and total and free float indicated for each activity:        -Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C. -Calculate the TF total float) and FF free float) values - indicated by y and z - for Task C.

(Multiple Choice)
4.9/5
(39)

The following software development plan is the basis for the next four questions The following software development plan is the basis for the next four questions   -The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame? -The client would like to have the completed software in 37 weeks. What is the likelihood the critical path will be completed in that time frame?

(Multiple Choice)
4.8/5
(35)

The following information is the basis for the next three questions. Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required. Activity Description Predeces sor Optimistic Most Lik ely Pessim istic A Digging - 2 3 4 B Replace line A 1 1.5 2 C Replace foot valve B .5 1 1.5 D Fill hole C 1.5 2 5.5 E Level soil D .5 1 1.5 F Reseed lawn E .4 .5 .6 -If the plumber and his crew begin working at 7:00 a.m., what time are they expected to finish?

(Multiple Choice)
5.0/5
(37)

Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method. Activity time estimates for the following project schedule have been developed using the PERT three-point time estimation method.      13. Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11? 13. Based on concepts presented in the text, what is the assumed likelihood Task D will be able to start at the end of Day 11?

(Multiple Choice)
4.9/5
(35)

Which of the following schedule display formats can require the use of dummy activities?

(Multiple Choice)
4.8/5
(32)

The following network is the basis for the next four questions: The following network is the basis for the next four questions:     -Which of these is the critical path for this project schedule? -Which of these is the critical path for this project schedule?

(Multiple Choice)
4.8/5
(35)

The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value. The following network shows a portion of an IT project involving programming, hardware installation, and implementation. As shown, programming and hardware installation are both estimated to be 52 days in duration. These estimates are not exact, given the uncertainty that can occur in any project environment, but they do share the same statistical distribution, with 52 as the median value.     Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation? Given what is covered in Chapter 6 regarding two tasks that merge into a common successor, what is the approximate probability that implementation can begin at the end of 52 days of concurrent work on programming and hardware installation?

(Multiple Choice)
4.9/5
(40)

The following network is the basis for the next four questions: The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have? -Assume all activities are scheduled to begin on their early start times. How much free float slack) does activity B have?

(Multiple Choice)
4.7/5
(35)

The following network is the basis for the next four questions: The following network is the basis for the next four questions:     -Assume all activities are scheduled to begin on their early start times. Circle the letter of each activity that has free float. -Assume all activities are scheduled to begin on their early start times. Circle the letter of each activity that has free float.

(Multiple Choice)
4.9/5
(32)

The following information is the basis for the next three questions. Jim and Carol Spalding have a crack in their waterline and need to replace it. This will require digging up the water line, replacing it, filling the hole, leveling the soil, and re-seeding the grass. The Spalding's plumber suggests that, since they have the well dug up, they should replace the foot valve in the well also. Below are the plumber's estimates of the time in hours) necessary to perform each of the activities required. Activity Description Predeces sor Optimistic Most Lik ely Pessim istic A Digging - 2 3 4 B Replace line A 1 1.5 2 C Replace foot valve B .5 1 1.5 D Fill hole C 1.5 2 5.5 E Level soil D .5 1 1.5 F Reseed lawn E .4 .5 .6 -Carol Spalding can't bear to see her lawn all dug up so she has decided to visit her mother on the day the work is to be done. Carol wants to return home at 6:45 p.m., what is the probability the work will be complete when Carol arrives home?

(Multiple Choice)
4.7/5
(33)

The table below shows PERT estimates te) for activities A through E.  Time estimates (days) \text { Time estimates (days) } Activity t(o) t(m) t(p) t(e) 4 5 9 ? 1 3 7 ? 3 6 10 ? 2 8 12 ? 1 4 6 ? Based on the table above, the te) for activities A, B and C are: .

(Multiple Choice)
4.8/5
(43)
Showing 1 - 20 of 21
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)