Deck 6: Project Time Management

Full screen (f)
exit full mode
Question
In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.
Use Space or
up arrow
down arrow
to flip the card.
Question
A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.
Question
After defining project activities, the next step in project time management is developing the schedule.
Question
Start-to-finish relationships are the most frequently used dependencies between activities.
Question
An activity is an element of work that has an expected duration, cost, and resource requirements.
Question
In project time management, the primary output of defining activities is a schedule management
plan.
Question
The arrows in a network diagram represent missed milestones in a project.
Question
In project time management, one should control the scheule before estimating the duration for each activity.
Question
Network diagrams are the preferred technique for showing activity sequencing.
Question
To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.
Question
A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.
Question
A dependency pertains to the sequencing of project activities or tasks.
Question
It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.
Question
In a Gantt chart, thick black bars represent milestones achieved in a project.
Question
In project time management, the next step after sequencing activities is to define these activities.
Question
A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.
Question
A merge occurs when one node precedes mutiple nodes.
Question
A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.
Question
Project schedules grow out of basic documents such as the project charter.
Question
Milestones are easy to achieve and are always achieved through one main activity.
Question
In project time management, a(n) _____ is an output of controlling the schedule

A) activity duration estimate
B) project management plan update
C) activity attribute
D) milestones list
Question
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.

A) estimating activity durations
B) developing the schedule
C) controlling the schedule
D) estimating activity resources
Question
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
Question
The critical path on a project can change as the project progresses.
Question
Critical chain scheduling assumes that resources multitask and maximizes multitasking.
Question
Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

A) Resource breakdown structure
B) Milestones list
C) Organizational process assets update
D) Project charter
Question
Knowing the amount of float allows project managers to know whether a project schedule is flexible.
Question
In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?

A) Planning schedule management
B) Developing the schedule
C) Controlling the schedule
D) Defining activities
Question
A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.
Question
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?

A) Defining activities
B) Sequencing activities
C) Planning schedule management
D) Estimating activity durations
Question
A backward pass through the network diagram determines the early start and early finish dates for each activity.
Question
The final process in project time management is developing the schedule.
Question
One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.
Question
Which of the following is a difference between an activity list and an activity attribute?

A) As opposed to an activity attribute, an activity list provides resource requirements and constraints related to activities.
B) An activity list provides a more concrete list of milestones for a project than an activity attribute.
C) An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not.
D) An activity attribute provides more schedule-related information about each activity than an activity list.
Question
Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?

A) Defining activities
B) Sequencing activities
C) Developing the schedule
D) Estimating activity durations
Question
In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual activities?

A) Defining activities
B) Sequencing activities
C) Planning schedule management
D) Estimating activity durations
Question
The first process involved in project time management is _____ .

A) defining activities
B) estimating activity durations
C) planning schedule management
D) sequencing activities
Question
In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?

A) Sequencing activities
B) Defining activities
C) Resource estimating activities
D) Estimating activity durations
Question
The technique of fast tracking can result in lengthening the project schedule.
Question
In a critical path analysis, the shortest path is what drives the completion date for the project.
Question
AOA network diagrams use only _____ dependencies.

A) start-to-start
B) finish-to-start
C) finish-to-finish
D) start-to-finish
Question
_____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

A) Gantt charts
B) Critical path analysis
C) Arrow diagramming method
D) PERT analysis
Question
A(n) _____ on a project is a significant event that normally has no duration.

A) milestone
B) activity attribute
C) activity sequence
D) schedule baseline
Question
Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?

A) Start-to-start
B) Finish-to-finish
C) Finish-to-start
D) Start-to-finish
Question
Which of the following is true of a finsih-to-finish dependency?

A) It is a dependency in which the "from" activity cannot start until the "to" activity or successor is started.
B) It is a dependency in which in which the "from" activity must finish before the "to" activity or successor can start.
C) It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
D) It is a dependency in which the "from" activity must start before the "to" activity can be finished.
Question
Which of the following dependencies involve relationships between project and non-project activities?

A) Mandatory
B) Discretionary
C) External
D) Inherent
Question
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.

A) defining activities
B) estimating activity durations
C) estimating activity resources
D) controlling the schedule
Question
In project time management, the next step after defining project activities is:

A) planning schedule management.
B) determining their dependencies.
C) controlling the schedule.
D) estimating activity duration.
Question
The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.

A) forward pass
B) backward pass
C) fast tracking
D) free slack
Question
Which of the following types of dependencies are inherent in the nature of work being performed on a project?

A) Mandatory
B) Discretionary
C) External
D) Random
Question
A network diagramming technique in which boxes represent activities is known as a(n) _____.

A) PDM
B) CPM
C) ADM
D) PERT
Question
_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.

A) Mandatory
B) Discretionary
C) External
D) Inherent
Question
Which of the following is one of the main outputs of estimating activity resources process?

A) Project documents update
B) Milestone list
C) Work breakdown structure
D) Activity duration estimate
Question
In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.

A) defining activities
B) sequencing activities
C) developing a schedule
D) estimating activity resources
Question
Which of the following is true of dummy activities?

A) They have long durations.
B) They show logical relationships between activities.
C) They have a large range of resources.
D) They have limited time periods.
Question
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.

A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest
Question
In an AOA network diagram, _____ occur when two or more activities follow a single node.

A) combinations
B) buffers
C) mergers
D) bursts
Question
_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.

A) Total slack
B) Free float
C) Backward pass
D) Forward pass
Question
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:

A) develop the schedule.
B) control the schedule.
C) determine their dependencies.
D) estimate the duration of activities.
Question
Which of the following is a network diagramming technique used primarily to predict total project duration?

A) Gantt chart
B) Critical path analysis
C) Resource breakdown structure
D) Arrow diagramming method
Question
The _____ is a tabulation of activities to be included on a project schedule.
Question
The activity list should include the _____, an activity identifier, and a brief description of the activity.
Question
_____ involves the processes required to ensure timely completion of a project.
Question
In a(n) _____ relationship, the "from" activity must start before the "to" activity can be finished.
Question
In project time management, the process of _____ involves deciding how many people, equipment, and materials a project team should use to perform project activities.
Question
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.

A) critical paths
B) feeding buffers
C) dummy activities
D) fast tracking
Question
In the activity defining process, the project team should review the _____ and activity attributes with project stakeholders before moving on to the next step in project time management.
Question
Which of the following is an output of schedule control?

A) Lessons-learned reports
B) Activity attributes
C) Resource requirements
D) Milestones list
Question
A draft schedule for a project is most likely to be found in a _____.

A) project buffer
B) project charter
C) resource breakdown structure
D) project's dummy activities list
Question
A similarity between the crashing technique and the fast tracking technique is that:

A) both spread out tasks over a long period of time to ensure the quality of work is maintained.
B) both invariably result in increases in total project costs.
C) both can shorten the time needed to finish a project.
D) both are network diagramming techniques used primarily to predict total project duration.
Question
Which of the following is a silimarity between scope control and schedule control?

A) Both are initial processes of project time management.
B) Both of their primary goals is to define project goals and miestones.
C) Both are portions of the integrated change control process under project integration management.
D) Both of these processes should occur before estimating activity durations.
Question
A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:

A) CPM addresses the risk associated with duration estimates whereas PERT does not.
B) unlike CPM, PERT estimates only when there is no risk of uncertainty.
C) CPM involves more work than PERT because it requires several duration estimates.
D) PERT uses different duration estimates whereas CPM uses one specific duration estimate.
Question
The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.

A) early finish date
B) late finish date
C) late start date
D) early start date
Question
_____ states that work expands to fill the time allowed.

A) Murphy's Law
B) Miller's Law
C) Parkinson's Law
D) Einstein's Law
Question
In a network diagram, a(n) _____ is the starting and ending point of an activity.
Question
Which of the following techniques involve doing activities in parallel that one would normally do in sequence?

A) Critical chain scheduling
B) Crashing
C) Fast tracking
D) PERT analysis
Question
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.

A) dependency
B) crashing
C) critical chain scheduling
D) feeding buffers
Question
In a project schedule, the variable that has the least amount of flexibility is _____.
Question
After reviewing the project management plan, project charter, enterprise environmental factors, and organizational process assets, the project team uses expert judgment, analytical techniques, and meetings to develop the _____.
Question
A(n) _____ is a schematic display of the logical relationships among project activities and
their sequencing.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/100
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: Project Time Management
1
In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.
False
The network diagram represents activities that must be done to complete the project. Not every item on the WBS needs to be shown on the network diagram; only activities with dependencies need to be shown.
2
A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.
True
A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates. It allows the project manager to monitor schedule progress on individual tasks and the whole project.
3
After defining project activities, the next step in project time management is developing the schedule.
False
After defining project activities, the next step in project time management is sequencing them or determining their dependencies.
4
Start-to-finish relationships are the most frequently used dependencies between activities.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
5
An activity is an element of work that has an expected duration, cost, and resource requirements.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
6
In project time management, the primary output of defining activities is a schedule management
plan.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
7
The arrows in a network diagram represent missed milestones in a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
8
In project time management, one should control the scheule before estimating the duration for each activity.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
9
Network diagrams are the preferred technique for showing activity sequencing.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
10
To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
11
A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
12
A dependency pertains to the sequencing of project activities or tasks.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
13
It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
14
In a Gantt chart, thick black bars represent milestones achieved in a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
15
In project time management, the next step after sequencing activities is to define these activities.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
16
A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
17
A merge occurs when one node precedes mutiple nodes.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
18
A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
19
Project schedules grow out of basic documents such as the project charter.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
20
Milestones are easy to achieve and are always achieved through one main activity.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
21
In project time management, a(n) _____ is an output of controlling the schedule

A) activity duration estimate
B) project management plan update
C) activity attribute
D) milestones list
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
22
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.

A) estimating activity durations
B) developing the schedule
C) controlling the schedule
D) estimating activity resources
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
23
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
24
The critical path on a project can change as the project progresses.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
25
Critical chain scheduling assumes that resources multitask and maximizes multitasking.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
26
Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

A) Resource breakdown structure
B) Milestones list
C) Organizational process assets update
D) Project charter
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
27
Knowing the amount of float allows project managers to know whether a project schedule is flexible.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
28
In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?

A) Planning schedule management
B) Developing the schedule
C) Controlling the schedule
D) Defining activities
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
29
A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
30
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?

A) Defining activities
B) Sequencing activities
C) Planning schedule management
D) Estimating activity durations
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
31
A backward pass through the network diagram determines the early start and early finish dates for each activity.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
32
The final process in project time management is developing the schedule.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
33
One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
34
Which of the following is a difference between an activity list and an activity attribute?

A) As opposed to an activity attribute, an activity list provides resource requirements and constraints related to activities.
B) An activity list provides a more concrete list of milestones for a project than an activity attribute.
C) An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not.
D) An activity attribute provides more schedule-related information about each activity than an activity list.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
35
Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?

A) Defining activities
B) Sequencing activities
C) Developing the schedule
D) Estimating activity durations
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
36
In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual activities?

A) Defining activities
B) Sequencing activities
C) Planning schedule management
D) Estimating activity durations
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
37
The first process involved in project time management is _____ .

A) defining activities
B) estimating activity durations
C) planning schedule management
D) sequencing activities
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
38
In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?

A) Sequencing activities
B) Defining activities
C) Resource estimating activities
D) Estimating activity durations
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
39
The technique of fast tracking can result in lengthening the project schedule.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
40
In a critical path analysis, the shortest path is what drives the completion date for the project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
41
AOA network diagrams use only _____ dependencies.

A) start-to-start
B) finish-to-start
C) finish-to-finish
D) start-to-finish
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
42
_____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

A) Gantt charts
B) Critical path analysis
C) Arrow diagramming method
D) PERT analysis
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
43
A(n) _____ on a project is a significant event that normally has no duration.

A) milestone
B) activity attribute
C) activity sequence
D) schedule baseline
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
44
Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?

A) Start-to-start
B) Finish-to-finish
C) Finish-to-start
D) Start-to-finish
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
45
Which of the following is true of a finsih-to-finish dependency?

A) It is a dependency in which the "from" activity cannot start until the "to" activity or successor is started.
B) It is a dependency in which in which the "from" activity must finish before the "to" activity or successor can start.
C) It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
D) It is a dependency in which the "from" activity must start before the "to" activity can be finished.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
46
Which of the following dependencies involve relationships between project and non-project activities?

A) Mandatory
B) Discretionary
C) External
D) Inherent
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
47
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.

A) defining activities
B) estimating activity durations
C) estimating activity resources
D) controlling the schedule
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
48
In project time management, the next step after defining project activities is:

A) planning schedule management.
B) determining their dependencies.
C) controlling the schedule.
D) estimating activity duration.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
49
The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.

A) forward pass
B) backward pass
C) fast tracking
D) free slack
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
50
Which of the following types of dependencies are inherent in the nature of work being performed on a project?

A) Mandatory
B) Discretionary
C) External
D) Random
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
51
A network diagramming technique in which boxes represent activities is known as a(n) _____.

A) PDM
B) CPM
C) ADM
D) PERT
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
52
_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.

A) Mandatory
B) Discretionary
C) External
D) Inherent
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
53
Which of the following is one of the main outputs of estimating activity resources process?

A) Project documents update
B) Milestone list
C) Work breakdown structure
D) Activity duration estimate
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
54
In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.

A) defining activities
B) sequencing activities
C) developing a schedule
D) estimating activity resources
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
55
Which of the following is true of dummy activities?

A) They have long durations.
B) They show logical relationships between activities.
C) They have a large range of resources.
D) They have limited time periods.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
56
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.

A) longest; longest
B) longest; shortest
C) shortest; longest
D) shortest; shortest
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
57
In an AOA network diagram, _____ occur when two or more activities follow a single node.

A) combinations
B) buffers
C) mergers
D) bursts
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
58
_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.

A) Total slack
B) Free float
C) Backward pass
D) Forward pass
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
59
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:

A) develop the schedule.
B) control the schedule.
C) determine their dependencies.
D) estimate the duration of activities.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
60
Which of the following is a network diagramming technique used primarily to predict total project duration?

A) Gantt chart
B) Critical path analysis
C) Resource breakdown structure
D) Arrow diagramming method
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
61
The _____ is a tabulation of activities to be included on a project schedule.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
62
The activity list should include the _____, an activity identifier, and a brief description of the activity.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
63
_____ involves the processes required to ensure timely completion of a project.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
64
In a(n) _____ relationship, the "from" activity must start before the "to" activity can be finished.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
65
In project time management, the process of _____ involves deciding how many people, equipment, and materials a project team should use to perform project activities.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
66
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.

A) critical paths
B) feeding buffers
C) dummy activities
D) fast tracking
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
67
In the activity defining process, the project team should review the _____ and activity attributes with project stakeholders before moving on to the next step in project time management.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
68
Which of the following is an output of schedule control?

A) Lessons-learned reports
B) Activity attributes
C) Resource requirements
D) Milestones list
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
69
A draft schedule for a project is most likely to be found in a _____.

A) project buffer
B) project charter
C) resource breakdown structure
D) project's dummy activities list
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
70
A similarity between the crashing technique and the fast tracking technique is that:

A) both spread out tasks over a long period of time to ensure the quality of work is maintained.
B) both invariably result in increases in total project costs.
C) both can shorten the time needed to finish a project.
D) both are network diagramming techniques used primarily to predict total project duration.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
71
Which of the following is a silimarity between scope control and schedule control?

A) Both are initial processes of project time management.
B) Both of their primary goals is to define project goals and miestones.
C) Both are portions of the integrated change control process under project integration management.
D) Both of these processes should occur before estimating activity durations.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
72
A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:

A) CPM addresses the risk associated with duration estimates whereas PERT does not.
B) unlike CPM, PERT estimates only when there is no risk of uncertainty.
C) CPM involves more work than PERT because it requires several duration estimates.
D) PERT uses different duration estimates whereas CPM uses one specific duration estimate.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
73
The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.

A) early finish date
B) late finish date
C) late start date
D) early start date
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
74
_____ states that work expands to fill the time allowed.

A) Murphy's Law
B) Miller's Law
C) Parkinson's Law
D) Einstein's Law
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
75
In a network diagram, a(n) _____ is the starting and ending point of an activity.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
76
Which of the following techniques involve doing activities in parallel that one would normally do in sequence?

A) Critical chain scheduling
B) Crashing
C) Fast tracking
D) PERT analysis
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
77
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.

A) dependency
B) crashing
C) critical chain scheduling
D) feeding buffers
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
78
In a project schedule, the variable that has the least amount of flexibility is _____.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
79
After reviewing the project management plan, project charter, enterprise environmental factors, and organizational process assets, the project team uses expert judgment, analytical techniques, and meetings to develop the _____.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
80
A(n) _____ is a schematic display of the logical relationships among project activities and
their sequencing.
Unlock Deck
Unlock for access to all 100 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 100 flashcards in this deck.