A(n) _____ for a project is the series of activities that determine the earliest time by which the project can be completed.

Free
(Short Answer)
4.9/5
(27)
Correct Answer:
Verified

critical path

In an AOA network diagram, _____ occur when two or more activities follow a single node.

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

D

A white diamond on a Tracking Gantt chart represents a(n) _____.

Free
(Short Answer)
4.9/5
(36)
Correct Answer:
Verified

slipped milestone

After defining project activities, the next step in project time management is developing the schedule.

(True/False)
4.8/5
(29)

_____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

(Multiple Choice)
5.0/5
(36)

The main disadvantage of crashing is that it lengthens the time needed to finish a project.

(True/False)
4.8/5
(39)

A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.

(True/False)
4.8/5
(35)

Which of the following is true of dummy activities?

(Multiple Choice)
4.9/5
(42)

Milestones are easy to achieve and are always achieved through one main activity.

(True/False)
4.7/5
(26)

What is the Theory of Constraints? Describe critical chain scheduling, an application of the Theory of Constraints.

(Essay)
4.8/5
(40)

_____ involves the processes required to ensure timely completion of a project.

(Short Answer)
4.8/5
(38)

The activity list should include the _____, an activity identifier, and a brief description of the activity.

(Short Answer)
4.7/5
(39)

Which of the following is one of the main outputs of estimating activity resources process?

(Multiple Choice)
4.7/5
(42)

_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.

(Multiple Choice)
4.9/5
(32)

After reviewing the project management plan, project charter, enterprise environmental factors, and organizational process assets, the project team uses expert judgment, analytical techniques, and meetings to develop the _____.

(Short Answer)
4.8/5
(38)

In a network diagram, a(n) _____ is the starting and ending point of an activity.

(Short Answer)
4.7/5
(36)

A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for a project.

(True/False)
4.8/5
(36)

The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.

(Multiple Choice)
4.8/5
(36)

A drawback of using _____ or sample files is that managers and their teams might rely heavily on them and ignore unique concerns for their particular projects.

(Short Answer)
4.7/5
(35)

A(n) _____ is a schematic display of the logical relationships among project activities and their sequencing.

(Short Answer)
4.7/5
(39)