Deck 16: Managing Projects
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Question
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/56
Play
Full screen (f)
Deck 16: Managing Projects
1
There are more resources required during the performance phase of a project than the project definition phase.
True
2
A critical path is composed entirely of critical activities.
True
3
In what way are projects and typical business activities similar?
A)For most companies,projects and typical business activities can be described as routine.
B)Both projects and typical business activities have a defined ending point at which time they are complete.
C)Projects and routine business activities require significant levels of cross-functional and inter-organizational coordination.
D)The successful completion of projects and business activities is essential to a firm's competitive position.
A)For most companies,projects and typical business activities can be described as routine.
B)Both projects and typical business activities have a defined ending point at which time they are complete.
C)Projects and routine business activities require significant levels of cross-functional and inter-organizational coordination.
D)The successful completion of projects and business activities is essential to a firm's competitive position.
D
4
Project planners develop a broad definition of what the project is and what its scope will be during the:
A)concept phase.
B)project definition phase.
C)planning phase.
D)performance phase.
A)concept phase.
B)project definition phase.
C)planning phase.
D)performance phase.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
5
One of the primary characteristics of projects as a form of work is the movement of personnel from project to project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
6
Your authors argue that the increasing numbers of middle management are attributable to their ability to manage projects.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
7
Program evaluation and review technique,PERT,is a network-based technique in which there are multiple time estimates for each activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
8
The earliest finish time of an activity is always later than its latest start time.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
9
Activities on the critical path may have positive or negative slack as long as the overall slack time of the critical path is zero.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
10
Key points in a project,such as when a major activity or phase is completed,are referred to as lodestones.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
11
Most project management software represents a project in AON format.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
12
The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
13
Crashing a project refers to the technique that minimizes completion cost of the project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
14
In the project definition phase,project planners identify,among other tasks,how to accomplish the work and how to organize for the project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
15
The Guide to the Project Management Body of Knowledge (PMBOK®)is divided into two main parts,the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
16
A project is a one-time undertaking designed to achieve a particular organization goal.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
17
A forward pass through a network is used to determine the earliest start and finish times for each project activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
18
Performance or time targets for each major group of activities in a project are set during the planning phase of a project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
19
The BEST use of a Gantt chart is to show precedence requirements for a project's constituent activities.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
20
The earliest start time of an activity is dependent on the earliest finish time of its immediate predecessors.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
21
This Gantt chart can be used to show: 
A)activity D must come before activity C.
B)activity F can be done at the same time as D.
C)activity E can begin as soon as activity A is complete.
D)activities D and B can be done simultaneously.

A)activity D must come before activity C.
B)activity F can be done at the same time as D.
C)activity E can begin as soon as activity A is complete.
D)activities D and B can be done simultaneously.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
22
A project is comprised of 6 activities that have durations and precedence requirements shown in the table.Which of these activities is not on the critical path? 
A)A
B)B
C)C
D)D

A)A
B)B
C)C
D)D
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
23
PERT is an acronym meaning:
A)Project Evaluation and Review Technique.
B)Project Execution and Review Technique.
C)Program Evaluation and Review Technique.
D)Plan Estimation and Review Technique.
A)Project Evaluation and Review Technique.
B)Project Execution and Review Technique.
C)Program Evaluation and Review Technique.
D)Plan Estimation and Review Technique.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
24
The budget estimates made during the concept phase are usually accurate to within:
A)20 percent.
B)30 percent.
C)40 percent.
D)50 percent.
A)20 percent.
B)30 percent.
C)40 percent.
D)50 percent.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
25
What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long? 
A)35
B)36
C)40
D)41

A)35
B)36
C)40
D)41
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
26
What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table? 
A)22
B)25
C)27
D)30

A)22
B)25
C)27
D)30
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
27
A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.

Which of the activities in this project has the greatest amount of slack?
A)B
B)C
C)D
D)E

Which of the activities in this project has the greatest amount of slack?

A)B
B)C
C)D
D)E
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
28
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.

What is the cheapest completion cost for the project if the contractor must complete all work in 45 days?
A)$550
B)$950
C)$1150
D)$1450


What is the cheapest completion cost for the project if the contractor must complete all work in 45 days?
A)$550
B)$950
C)$1150
D)$1450
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
29
A(n)________ is a graphical tool that should be used to show a project's progress as time elapses.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
30
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.The fixed cost for being on site is $450.What is the lowest total completion cost for the project?

A)$10,600
B)$11,000
C)$11,400
D)$12,000


A)$10,600
B)$11,000
C)$11,400
D)$12,000
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
31
A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.

Which of these statements is BEST?
A)Only four of these activities have zero slack.
B)The late finish of D minus the late finish of C is less than the slack of B.
C)B's late start plus its slack equals F's late finish.
D)The sum of the late start values for activities A through E is less than the sum of the late start values for F and G.

Which of these statements is BEST?
A)Only four of these activities have zero slack.
B)The late finish of D minus the late finish of C is less than the slack of B.
C)B's late start plus its slack equals F's late finish.
D)The sum of the late start values for activities A through E is less than the sum of the late start values for F and G.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
32
During the ________,project planners identify how to accomplish the work,how to organize for the project,and the key personnel and resources needed.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
33
A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.

Which of these activities has slack?
A)G
B)E
C)F
D)D

Which of these activities has slack?
A)G
B)E
C)F
D)D
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
34
A performance or time target for each major group of activities in a project is a(n)________.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
35
An expectation that a new building's foundation would be poured and cured by the end of the year is an example of a(n):
A)activity.
B)scope.
C)milestone.
D)precedence.
A)activity.
B)scope.
C)milestone.
D)precedence.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
36
The actual work gets done during the ________ phase of a project.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
37
What is the total cost to complete this project as quickly as possible if each day on site costs $1000?
A)$43,100
B)$40,300
C)$39,300
D)$41,900
A)$43,100
B)$40,300
C)$39,300
D)$41,900
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
38
Work on a project's constituent activities begins in the project's:
A)planning phase.
B)concept phase.
C)post-completion phase.
D)performance phase.
A)planning phase.
B)concept phase.
C)post-completion phase.
D)performance phase.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
39
What is the latest that activity D can start if A is 5 days,B is 7 days,C is 4 days,D is 5 days,E is 7 days,and F is 6 days long? 
A)14
B)15
C)16
D)17

A)14
B)15
C)16
D)17
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
40
How many days can this project be shortened if money is no object?
A)6 days
B)9 days
C)10 days
D)13 days
A)6 days
B)9 days
C)10 days
D)13 days
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
41
The project shown below has crash costs as shown in the table.What is the minimum completion cost for this project that has a fixed cost of $1000 per day?



Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
42
An activity's length added to its early start time yields the ________.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
43
The longest path in a network from the start of a project to the end of a project is ________.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
44
What are the early and late start and finish times for all of these activities?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
45
________ is a technique to shorten the overall length of the project that usually involves a trade-off between time and cost.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
46
Discuss the recent business trends that have increased the attention and interest in project management skills.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
47
The professional organization that serves the needs of project management professionals is ________.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
48
What are the phases of a project and the activities within each?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
49
Complete this table containing early and late start times and activity lengths.


Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
50
A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.

Develop a Gantt chart for this project and indicate the finish times for each activity.

Develop a Gantt chart for this project and indicate the finish times for each activity.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
51
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.

You have been given a budget of $2500 and instructed to complete the project as quickly as you can using that amount.Which activities do you expedite and what is the final cost and project duration?


You have been given a budget of $2500 and instructed to complete the project as quickly as you can using that amount.Which activities do you expedite and what is the final cost and project duration?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
52
A project is composed of the twelve activities shown in the table.What are the early and late start times for each of these activities?


Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
53
A project represented by the activities shown in this table must meet a deadline of 51 days.Sketch the network and determine the critical path.Using the crash costs and minimum activity lengths shown in the table,determine which activities to shorten and provide the total cost of finishing this project in 51 days.


Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
54
In what ways are projects distinct from typical business activities?
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
55
For critical path activities,slack is ________.
Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck
56
Given the early and late finish times for each of these activities,what are the activity lengths?


Unlock Deck
Unlock for access to all 56 flashcards in this deck.
Unlock Deck
k this deck