Exam 16: Managing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

A project is composed of the twelve activities shown in the table.What are the early and late start times for each of these activities? A project is composed of the twelve activities shown in the table.What are the early and late start times for each of these activities?

Free
(Short Answer)
4.9/5
(24)
Correct Answer:
Verified

A forward pass through a network is used to determine the earliest start and finish times for each project activity.

Free
(True/False)
4.8/5
(32)
Correct Answer:
Verified

True

A performance or time target for each major group of activities in a project is a(n)________.

Free
(Short Answer)
4.9/5
(34)
Correct Answer:
Verified

milestone

Performance or time targets for each major group of activities in a project are set during the planning phase of a project.

(True/False)
4.8/5
(38)

What is the latest that activity D can start if A is 5 days,B is 7 days,C is 4 days,D is 5 days,E is 7 days,and F is 6 days long? What is the latest that activity D can start if A is 5 days,B is 7 days,C is 4 days,D is 5 days,E is 7 days,and F is 6 days long?

(Multiple Choice)
4.8/5
(31)

Discuss the recent business trends that have increased the attention and interest in project management skills.

(Essay)
4.8/5
(47)

The project shown below has crash costs as shown in the table.What is the minimum completion cost for this project that has a fixed cost of $1000 per day? The project shown below has crash costs as shown in the table.What is the minimum completion cost for this project that has a fixed cost of $1000 per day?    The project shown below has crash costs as shown in the table.What is the minimum completion cost for this project that has a fixed cost of $1000 per day?

(Essay)
4.8/5
(41)

A project is comprised of 6 activities that have durations and precedence requirements shown in the table.Which of these activities is not on the critical path? A project is comprised of 6 activities that have durations and precedence requirements shown in the table.Which of these activities is not on the critical path?

(Multiple Choice)
4.9/5
(36)

What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long? What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long?

(Multiple Choice)
4.8/5
(34)

Project planners develop a broad definition of what the project is and what its scope will be during the:

(Multiple Choice)
4.8/5
(27)

Most project management software represents a project in AON format.

(True/False)
4.8/5
(29)

An expectation that a new building's foundation would be poured and cured by the end of the year is an example of a(n):

(Multiple Choice)
5.0/5
(39)

A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below. A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.    -Which of these statements is BEST? -Which of these statements is BEST?

(Multiple Choice)
4.8/5
(34)

________ is a technique to shorten the overall length of the project that usually involves a trade-off between time and cost.

(Short Answer)
4.8/5
(42)

PERT is an acronym meaning:

(Multiple Choice)
4.9/5
(32)

The Guide to the Project Management Body of Knowledge (PMBOK®)is divided into two main parts,the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.

(True/False)
4.7/5
(31)

A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below. A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.    -Which of these activities has slack? -Which of these activities has slack?

(Multiple Choice)
4.8/5
(35)

The budget estimates made during the concept phase are usually accurate to within:

(Multiple Choice)
4.7/5
(35)

What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table? What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table?

(Multiple Choice)
4.7/5
(36)

What is the total cost to complete this project as quickly as possible if each day on site costs $1000?

(Multiple Choice)
4.8/5
(26)
Showing 1 - 20 of 56
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)