Deck 14: Materials and Resource Requirements Planning

Full screen (f)
exit full mode
Question
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MSP quantity for week 4?</strong> A)500 B)400 C)450 D)50 <div style=padding-top: 35px> Using a lot-for-lot rule, what is the MSP quantity for week 4?

A)500
B)400
C)450
D)50
Use Space or
up arrow
down arrow
to flip the card.
Question
If the cumulative lead time is 8 weeks, to be feasible the MPS planning horizon must be:

A)Exactly 8 weeks.
B)At least 8 weeks.
C)Less than 8 weeks.
D)At least 16 weeks.
Question
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MPS quantity for period 1?</strong> A)90 B)80 C)100 D)40 <div style=padding-top: 35px> Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)90
B)80
C)100
D)40
Question
End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units. <strong>End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units.   What is the gross requirement for part E?</strong> A) 175 B) 275 C) 375 D) 250 <div style=padding-top: 35px> What is the gross requirement for part E?

A) 175
B) 275
C) 375
D) 250
Question
Planning for which of the following products would see the LEAST benefit from the use of an MRP system?

A)Microwave ovens
B)Mobile phones
C)Shampoo
D)Power lawnmowers
Question
Jones Company uses widgets as component parts. In a particular week it has gross requirements for 250 units of widgets, beginning inventory of 50 widgets, and scheduled receipts of 350 widgets. Available inventory for the next period is:

A)650.
B)50.
C)250.
D)150.
Question
The longest lead time path in the BOM is the:

A)Time bucket.
B)Planning horizon.
C)Time window.
D)Cumulative lead time.
Question
End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units. <strong>End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units.   What is the net requirement for part C?</strong> A) 70 units B) 200 units C) 125 units D) 100 units <div style=padding-top: 35px> What is the net requirement for part C?

A) 70 units
B) 200 units
C) 125 units
D) 100 units
Question
MRP is a process that would be most applicable in which situation?

A) Planning requirements for repair parts for production equipment in a manufacturing plant.
B) Planning requirements for safety stocks of finished goods in a distribution center.
C) Planning requirements for bicycle seats in a bicycle production plant.
D) A and C.
E) None of these.
Question
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   What is the available to promise for period 2?</strong> A)0. B)-20. C)20. D)None of these. <div style=padding-top: 35px> What is the available to promise for period 2?

A)0.
B)-20.
C)20.
D)None of these.
Question
Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items. <strong>Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items.  </strong> A)16 B)34 C)52 D)104 <div style=padding-top: 35px>

A)16
B)34
C)52
D)104
Question
The quantities of end items to be completed in each time period into the future is shown in a(n):

A)MRP.
B)MPS.
C)BOM.
D)ERP.
Question
Significant changes in an MPS quantity several weeks into the planning horizon can:

A)Make the MRP more accurate.
B)Cause inconsistencies in the MRP.
C)Reduce stockouts.
D)Increase safety stock.
Question
Which of the following is NOT included in the information about the inventory records file for an item?

A)Safety stock
B)Preferred order quantity
C)Net requirements
D)Lead time
Question
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Based on the information in the MPS, what is the amount that is available to promise in week 4?</strong> A)1,200 B)700 C)500 D)1,500 <div style=padding-top: 35px> Based on the information in the MPS, what is the amount that is available to promise in week 4?

A)1,200
B)700
C)500
D)1,500
Question
Which of the following is NOT an input into the MRP?

A)Bill of materials
B)Inventory records file
C)Master production schedule
D)Planned order release
Question
A bill-of-materials file contains:

A) Invoices for materials that must be paid in this period.
B) Lists of materials required to produce end item products.
C) Accounts payable for materials.
D) A and B.
Question
An MRP record for a motor is shown in the following table. <strong>An MRP record for a motor is shown in the following table.   What is the planned order release for week 4?</strong> A)0 B)10,000 C)8,000 D)6,000 <div style=padding-top: 35px> What is the planned order release for week 4?

A)0
B)10,000
C)8,000
D)6,000
Question
Materials requirement planning (MRP) systems are used primarily to:

A)Plan materials.
B)Plan lead time.
C)Plan production.
D)Plan distribution.
E)A and C
Question
End item A is made by assembling 2 of part B and 3 of part C. Part C is made from 2 of component D and 2 of component E. Component D is considered to be a:

A) Level 0.
B) Level 1 input.
C) Level 2 input.
D) Level 3 input.
Question
The following table shows capacity requirements data for making table tops. <strong>The following table shows capacity requirements data for making table tops.   Which of the following is TRUE?</strong> A)Overtime is needed in day 1. B)Capacity exactly meets demand in day 5. C)All of the excess demand in days 4 and 5 can be shifted to day 3. D)New machines are needed. <div style=padding-top: 35px> Which of the following is TRUE?

A)Overtime is needed in day 1.
B)Capacity exactly meets demand in day 5.
C)All of the excess demand in days 4 and 5 can be shifted to day 3.
D)New machines are needed.
Question
Rough-cut capacity planning does all of the following EXCEPT:

A)Determines if a work center has the capacity to implement the MRP plan.
B)Uses planned order releases and scheduled receipts to estimate work center loads.
C)Develops a load profile.
D)Recalculates the MRP plan.
Question
The following table shows capacity requirements data for making Blodgetts. <strong>The following table shows capacity requirements data for making Blodgetts.   A load profile would show:</strong> A)Load above capacity in periods 3 and 5. B)Load below capacity in periods 1 and 3. C)Load never is exactly equal to capacity in all periods. D)None of these. <div style=padding-top: 35px> A load profile would show:

A)Load above capacity in periods 3 and 5.
B)Load below capacity in periods 1 and 3.
C)Load never is exactly equal to capacity in all periods.
D)None of these.
Question
Constant changing of the master schedule and the resulting changes in the requirements for components is referred to as:

A)Master schedule dynamics.
B)System nervousness.
C)Bad planning.
D)MRP failure.
Question
Benefits of ERP systems include all of the following EXCEPT:

A)Easy implementation.
B)Fewer data entry errors.
C)More informed business decisions.
D)Improved customer service.
Question
Advanced planning and scheduling systems:

A)Use logic similar to the logic found in MRP.
B)Consolidate all business planning systems and data throughout an organization.
C)Integrate materials and capacity planning into one system.
D)A and C
E)All of these.
Question
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers. The type of system Zanda should consider is known as:

A)CRP.
B)DRP.
C)MRP.
D)ERP.
Question
Software that consolidates all of the business planning systems and data throughout an organization is:

A)MPS.
B)MRP.
C)DRP.
D)ERP.
Question
The positioning and replenishment of finished goods inventories at the retail level can be determined using:

A)MRP.
B)CRP.
C)DRP.
D)RFID.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/29
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 14: Materials and Resource Requirements Planning
1
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MSP quantity for week 4?</strong> A)500 B)400 C)450 D)50 Using a lot-for-lot rule, what is the MSP quantity for week 4?

A)500
B)400
C)450
D)50
500
2
If the cumulative lead time is 8 weeks, to be feasible the MPS planning horizon must be:

A)Exactly 8 weeks.
B)At least 8 weeks.
C)Less than 8 weeks.
D)At least 16 weeks.
At least 8 weeks.
3
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MPS quantity for period 1?</strong> A)90 B)80 C)100 D)40 Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)90
B)80
C)100
D)40
80
4
End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units. <strong>End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units.   What is the gross requirement for part E?</strong> A) 175 B) 275 C) 375 D) 250 What is the gross requirement for part E?

A) 175
B) 275
C) 375
D) 250
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
5
Planning for which of the following products would see the LEAST benefit from the use of an MRP system?

A)Microwave ovens
B)Mobile phones
C)Shampoo
D)Power lawnmowers
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
6
Jones Company uses widgets as component parts. In a particular week it has gross requirements for 250 units of widgets, beginning inventory of 50 widgets, and scheduled receipts of 350 widgets. Available inventory for the next period is:

A)650.
B)50.
C)250.
D)150.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
7
The longest lead time path in the BOM is the:

A)Time bucket.
B)Planning horizon.
C)Time window.
D)Cumulative lead time.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
8
End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units. <strong>End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units.   What is the net requirement for part C?</strong> A) 70 units B) 200 units C) 125 units D) 100 units What is the net requirement for part C?

A) 70 units
B) 200 units
C) 125 units
D) 100 units
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
9
MRP is a process that would be most applicable in which situation?

A) Planning requirements for repair parts for production equipment in a manufacturing plant.
B) Planning requirements for safety stocks of finished goods in a distribution center.
C) Planning requirements for bicycle seats in a bicycle production plant.
D) A and C.
E) None of these.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
10
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   What is the available to promise for period 2?</strong> A)0. B)-20. C)20. D)None of these. What is the available to promise for period 2?

A)0.
B)-20.
C)20.
D)None of these.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
11
Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items. <strong>Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items.  </strong> A)16 B)34 C)52 D)104

A)16
B)34
C)52
D)104
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
12
The quantities of end items to be completed in each time period into the future is shown in a(n):

A)MRP.
B)MPS.
C)BOM.
D)ERP.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
13
Significant changes in an MPS quantity several weeks into the planning horizon can:

A)Make the MRP more accurate.
B)Cause inconsistencies in the MRP.
C)Reduce stockouts.
D)Increase safety stock.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
14
Which of the following is NOT included in the information about the inventory records file for an item?

A)Safety stock
B)Preferred order quantity
C)Net requirements
D)Lead time
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
15
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Based on the information in the MPS, what is the amount that is available to promise in week 4?</strong> A)1,200 B)700 C)500 D)1,500 Based on the information in the MPS, what is the amount that is available to promise in week 4?

A)1,200
B)700
C)500
D)1,500
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
16
Which of the following is NOT an input into the MRP?

A)Bill of materials
B)Inventory records file
C)Master production schedule
D)Planned order release
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
17
A bill-of-materials file contains:

A) Invoices for materials that must be paid in this period.
B) Lists of materials required to produce end item products.
C) Accounts payable for materials.
D) A and B.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
18
An MRP record for a motor is shown in the following table. <strong>An MRP record for a motor is shown in the following table.   What is the planned order release for week 4?</strong> A)0 B)10,000 C)8,000 D)6,000 What is the planned order release for week 4?

A)0
B)10,000
C)8,000
D)6,000
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
19
Materials requirement planning (MRP) systems are used primarily to:

A)Plan materials.
B)Plan lead time.
C)Plan production.
D)Plan distribution.
E)A and C
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
20
End item A is made by assembling 2 of part B and 3 of part C. Part C is made from 2 of component D and 2 of component E. Component D is considered to be a:

A) Level 0.
B) Level 1 input.
C) Level 2 input.
D) Level 3 input.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
21
The following table shows capacity requirements data for making table tops. <strong>The following table shows capacity requirements data for making table tops.   Which of the following is TRUE?</strong> A)Overtime is needed in day 1. B)Capacity exactly meets demand in day 5. C)All of the excess demand in days 4 and 5 can be shifted to day 3. D)New machines are needed. Which of the following is TRUE?

A)Overtime is needed in day 1.
B)Capacity exactly meets demand in day 5.
C)All of the excess demand in days 4 and 5 can be shifted to day 3.
D)New machines are needed.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
22
Rough-cut capacity planning does all of the following EXCEPT:

A)Determines if a work center has the capacity to implement the MRP plan.
B)Uses planned order releases and scheduled receipts to estimate work center loads.
C)Develops a load profile.
D)Recalculates the MRP plan.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
23
The following table shows capacity requirements data for making Blodgetts. <strong>The following table shows capacity requirements data for making Blodgetts.   A load profile would show:</strong> A)Load above capacity in periods 3 and 5. B)Load below capacity in periods 1 and 3. C)Load never is exactly equal to capacity in all periods. D)None of these. A load profile would show:

A)Load above capacity in periods 3 and 5.
B)Load below capacity in periods 1 and 3.
C)Load never is exactly equal to capacity in all periods.
D)None of these.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
24
Constant changing of the master schedule and the resulting changes in the requirements for components is referred to as:

A)Master schedule dynamics.
B)System nervousness.
C)Bad planning.
D)MRP failure.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
25
Benefits of ERP systems include all of the following EXCEPT:

A)Easy implementation.
B)Fewer data entry errors.
C)More informed business decisions.
D)Improved customer service.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
26
Advanced planning and scheduling systems:

A)Use logic similar to the logic found in MRP.
B)Consolidate all business planning systems and data throughout an organization.
C)Integrate materials and capacity planning into one system.
D)A and C
E)All of these.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
27
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers. The type of system Zanda should consider is known as:

A)CRP.
B)DRP.
C)MRP.
D)ERP.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
28
Software that consolidates all of the business planning systems and data throughout an organization is:

A)MPS.
B)MRP.
C)DRP.
D)ERP.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
29
The positioning and replenishment of finished goods inventories at the retail level can be determined using:

A)MRP.
B)CRP.
C)DRP.
D)RFID.
Unlock Deck
Unlock for access to all 29 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 29 flashcards in this deck.