Deck 26: Lean Manufacturing and Activity Analysis

Full screen (f)
exit full mode
Question
In the lean principles philosophy,unexpected downtime is the result of unreliable processes.
Use Space or
up arrow
down arrow
to flip the card.
Question
Long setups and large batch sizes result in smaller inventories.
Question
Reducing wait time is directly linked to reducing inventory.
Question
All lead times are considered to be value-added lead time.
Question
Within-batch wait time increases total lead time.
Question
A setup is the time required to prepare an operation for a new production run.
Question
Lean manufacturing focuses on reducing time,cost,and poor quality in processes.
Question
Lean manufacturing favors organizing work around processes rather than around products.
Question
Lead time reduction can be a cost-saving goal for any processed item.
Question
Lead time includes both value-added time and non-value-added time.
Question
The lean philosophy views inventory as a necessary buffer to protect against process problems.
Question
Lean manufacturing favors organizing work around products rather than around processes.
Question
Reducing wait time is not linked to reducing inventory.
Question
A make-to-order company matches its production schedules to actual customer orders.
Question
Lean manufacturing is also called make-to-stock manufacturing.
Question
Lean manufacturing is also called make-to-order manufacturing.
Question
Large batch sizes increase lead time.
Question
Employee involvement in a product-oriented factory emphasizes employee teams,rather than individual employees.
Question
Lead time is the process time between start and completion.
Question
The lean manufacturing philosophy views inventory as an unnecessary waste of resources.
Question
In a lean environment,raw materials are delivered less frequently than in a traditional environment.
Question
In a lean environment,operations only respond to customer orders.
Question
In a push manufacturing system,raw materials are released to production based on actual customer orders.
Question
Under the lean production concept,employees are better utilized if they are experts in one operation rather than wasting time training them to learn various production operations.
Question
In a lean environment,process problems are more visible than they are in a traditional environment.
Question
Employee involvement does not include performing any indirect manufacturing functions.
Question
Push manufacturing is also referred to as make-to-order processing.
Question
In a pull manufacturing system,raw materials are released to production based on actual customer orders.
Question
In a lean environment,raw materials are delivered more frequently than in a traditional environment.
Question
Push manufacturing (made-to-stock)is a traditional approach to manufacturing.
Question
Make-to-order companies produce mainly to stock inventory.
Question
In a push manufacturing system,raw materials are released to production based on forecasted demand.
Question
In a lean environment,process problems are less visible than they are in a traditional environment.
Question
One inherent risk to using lean philosophy is that companies are at higher risk of inventory shortage during volatile times such as strikes,weather,etc.than when using the traditional philosophy.
Question
Make-to-order companies typically produce in small batch sizes.
Question
In a pull manufacturing system,raw materials are released to production based on forecasted demand.
Question
Setups are a significant time-consuming activity in traditional production environments.
Question
A process-oriented layout segments production facilities into functional departments.
Question
Maximum effectiveness and efficiency are reached when the lean philosophy is used by both manufacturers and their suppliers.
Question
Maximum effectiveness and efficiency are reached when the lean philosophy is used mainly by manufacturers.
Question
Inventory reduction is a ____ principle.

A) lean
B) traditional processing
C) economic
D) wait time
Question
Which of the following is an example of value-added time?

A) Processing time
B) Wait time during inspection
C) Wait time in inventory
D) Both B and C
Question
Which of the following are features of the lean manufacturing system?

(a)maintaining excess inventory to ensure that products will always be available
(b)cross training of employees
(c)giving employees additional authority and responsibility
(d)product-oriented layout
(e)increased set-up time
Question
Christmas Express makes wreaths in batch sizes of 12.The cutting & assembly process takes 8 minutes per wreath and the decorating process time is 10 minutes per wreath.It takes 12 minutes to move the wreaths from the cutting & assembly process to the decorating process.

(a)Compute the value-added,non-value-added,and the total lead time of the wreath process.
(b)Compute the value-added ratio.Round to the nearest decimal.
Question
Examples of transforming a traditional manufacturing environment to a lean environment is to do all of the following except

A) form partnerships with reliable suppliers.
B) reorganize operational processes to organized product lines.
C) train employees to perform various operations.
D) increase raw materials to produce more,thereby increasing finished goods inventory.
Question
____ manufacturing philosophy emphasizes quality and zero defects.

A) Traditional
B) Lean
C) Zero-Based
D) Chinese
Question
Which of the following drives work-in-process inventory levels higher?

A) Machine breakdowns
B) Production rate losses
C) Rework processes
D) All of the above
Question
Which of the following is characteristic of a lean production layout?

A) Decentralized maintenance and small production batches
B) Decemtralized maintenance and organization around processes
C) Organization around processes and small production batches
D) Large production batches and organization around processes.
Question
The lean philosophy attempts to reduce setup times,which will:

A) increase batch sizes
B) not affect batch sizes
C) increase within-batch wait time
D) decrease within-batch wait time
Question
Which of the following is considered non-value-added lead time?

A) packing
B) moving from process to process
C) converting raw materials to finished product
D) all of the above
Question
What do lean manufacturers demand from their vendors?

A) High quality materials
B) Low cost materials
C) On-time deliveries
D) All of the above
Question
How are the objectives of lean manufacturing achieved?

A) Product-oriented production layout
B) Employee involvement
C) Supplier partnering
D) All of the above
Question
Under a lean environment,employees have the responsibility and authority to

A) purchase inventory.
B) determine output amounts.
C) make decisions about operations,rather than waiting for management.
D) make engineering changes.
Question
In a lean environment,process problems are more visible than they are in a traditional environment because:

A) inventories are maintained at higher levels.
B) process problems cause production to shut down immediately.
C) the push manufacturing system leads to increased inventory level.
D) the lack of work in process inventory creates problems.
Question
Which of the following results in long lead time?

A) long setup times
B) large batch sizes
C) large inventories
D) all of the above
Question
Lean manufacturing philosophy reduces all of the following except

A) inventory
B) setup time
C) lead time
D) conversion costs
Question
Traditional manufacturing emphasizes all of the following except

A) team oriented employee involvement
B) process-oriented layout
C) push manufacturing
D) cost accumulation by department
Question
Set up time is disregarded as an improvement priority under the ____ manufacturing concept.

A) traditional
B) lean
C) total quality management
D) product cost
Question
Which of the following is (are)objective(s)of lean manufacturing?

A) eliminating waste
B) increasing inventory levels
C) increased production speed
D) all of the above
Question
____ manufacturing deals with several suppliers in hopes of finding the best price.

A) Traditional
B) Lean
C) Economic
D) Productivity improvement
Question
Financial accounting information is used more often for long-term operating decisions and nonfinancial information is used more often for day-to-day decisions.
Question
A backflush accounting system uses work in process inventories as control points between each process step.
Question
In a lean environment,the journal entry to record conversion costs would include a debit to the raw and in process inventory account.
Question
In a lean system,there are more transactions to record than there are in a traditional system.
Question
In a lean system,the work in process and raw materials inventory accounts are combined.
Question
In a lean system,direct labor is included in conversion costs.
Question
In a lean system,indirect labor is traced directly to product cells.
Question
A nonfinancial measure is operating information that has not been translated into dollars.
Question
In a lean system,there are fewer transactions to record than there are in a traditional system.
Question
A college would like to increase enrollment by streamlining the enrollment process.Which of the following would not fall in line with the college goal?

A) Reduce the requirements necessary to enroll.
B) Relocate counselors,academic advisors,and financial aid specialists for a major to a central location.
C) Cross-train counselors,academic advisors,and financial aid specialists.
D) All of these choices would fall in line with the college goal.
Question
In a lean environment,the journal entry to record raw materials purchases would include a credit to the raw materials inventory account.
Question
The budgeted cell conversion cost rate is very similar to the predetermined factory rate because both include only factory overhead costs.
Question
Nonfinancial accounting information is used more often for long-term operating decisions than is financial information.
Question
Which of the following is characteristic of the lean system?

A) Fewer work in process account transactions.
B) Work in process and raw materials accounts combined.
C) Elimination of the direct labor account.
D) All of the above.
Question
A lean nonmanufacturing process can be accomplished by consolidating,in one area,all of the services provided to a customer.
Question
In a lean environment,the journal entry to record raw materials purchases would include a debit to the raw and in process inventory account.
Question
In a lean environment,the journal entry to record conversion costs would include a debit to the manufacturing overhead control account.
Question
A local college is aggressively working to reduce the time it takes students to enroll for each semester.Which of the following changes would not help achieve this goal?

A) Counselors are specializing in common degree plans
B) One application is good at the community college and at the transferring university
C) A one stop area includes admissions,advising,registration and student ID's
D) Having more number of staff to help facilitate admission process
Question
Which of the following is characteristic of the traditional cost system?

A) Many work in process account transactions.
B) Reliance on financial performance measures.
C) Many process control points.
D) All of the above.
Question
Extreme Wreaths,Inc.makes wreaths in batch sizes of 15 at a time.The cutting & assembly process takes 10 minutes per wreath,and the decorating process time is 7 minutes per wreath.It takes 5 minutes to move the wreaths from the cutting & assembly process to the decorating process.

In a effort to improve the lead time,the company has tried reducing the batch size to 10 units.The new process is as follows: cutting & assembly process - 8 minutes.The decorating process is still 7 minutes per wreath.It takes 5 minutes to move the wreaths from the cutting & assembly process to the decorating process.

(a)Compute the value-added,non-value-added,and the total lead time of the wreath process for both the old and the new manufacturing process.
(b)Compute the value-added ratio for both the old and new process.Round to the nearest decimal.
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/121
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 26: Lean Manufacturing and Activity Analysis
1
In the lean principles philosophy,unexpected downtime is the result of unreliable processes.
True
2
Long setups and large batch sizes result in smaller inventories.
False
3
Reducing wait time is directly linked to reducing inventory.
True
4
All lead times are considered to be value-added lead time.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
5
Within-batch wait time increases total lead time.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
6
A setup is the time required to prepare an operation for a new production run.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
7
Lean manufacturing focuses on reducing time,cost,and poor quality in processes.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
8
Lean manufacturing favors organizing work around processes rather than around products.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
9
Lead time reduction can be a cost-saving goal for any processed item.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
10
Lead time includes both value-added time and non-value-added time.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
11
The lean philosophy views inventory as a necessary buffer to protect against process problems.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
12
Lean manufacturing favors organizing work around products rather than around processes.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
13
Reducing wait time is not linked to reducing inventory.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
14
A make-to-order company matches its production schedules to actual customer orders.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
15
Lean manufacturing is also called make-to-stock manufacturing.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
16
Lean manufacturing is also called make-to-order manufacturing.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
17
Large batch sizes increase lead time.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
18
Employee involvement in a product-oriented factory emphasizes employee teams,rather than individual employees.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
19
Lead time is the process time between start and completion.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
20
The lean manufacturing philosophy views inventory as an unnecessary waste of resources.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
21
In a lean environment,raw materials are delivered less frequently than in a traditional environment.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
22
In a lean environment,operations only respond to customer orders.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
23
In a push manufacturing system,raw materials are released to production based on actual customer orders.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
24
Under the lean production concept,employees are better utilized if they are experts in one operation rather than wasting time training them to learn various production operations.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
25
In a lean environment,process problems are more visible than they are in a traditional environment.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
26
Employee involvement does not include performing any indirect manufacturing functions.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
27
Push manufacturing is also referred to as make-to-order processing.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
28
In a pull manufacturing system,raw materials are released to production based on actual customer orders.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
29
In a lean environment,raw materials are delivered more frequently than in a traditional environment.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
30
Push manufacturing (made-to-stock)is a traditional approach to manufacturing.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
31
Make-to-order companies produce mainly to stock inventory.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
32
In a push manufacturing system,raw materials are released to production based on forecasted demand.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
33
In a lean environment,process problems are less visible than they are in a traditional environment.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
34
One inherent risk to using lean philosophy is that companies are at higher risk of inventory shortage during volatile times such as strikes,weather,etc.than when using the traditional philosophy.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
35
Make-to-order companies typically produce in small batch sizes.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
36
In a pull manufacturing system,raw materials are released to production based on forecasted demand.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
37
Setups are a significant time-consuming activity in traditional production environments.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
38
A process-oriented layout segments production facilities into functional departments.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
39
Maximum effectiveness and efficiency are reached when the lean philosophy is used by both manufacturers and their suppliers.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
40
Maximum effectiveness and efficiency are reached when the lean philosophy is used mainly by manufacturers.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
41
Inventory reduction is a ____ principle.

A) lean
B) traditional processing
C) economic
D) wait time
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
42
Which of the following is an example of value-added time?

A) Processing time
B) Wait time during inspection
C) Wait time in inventory
D) Both B and C
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
43
Which of the following are features of the lean manufacturing system?

(a)maintaining excess inventory to ensure that products will always be available
(b)cross training of employees
(c)giving employees additional authority and responsibility
(d)product-oriented layout
(e)increased set-up time
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
44
Christmas Express makes wreaths in batch sizes of 12.The cutting & assembly process takes 8 minutes per wreath and the decorating process time is 10 minutes per wreath.It takes 12 minutes to move the wreaths from the cutting & assembly process to the decorating process.

(a)Compute the value-added,non-value-added,and the total lead time of the wreath process.
(b)Compute the value-added ratio.Round to the nearest decimal.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
45
Examples of transforming a traditional manufacturing environment to a lean environment is to do all of the following except

A) form partnerships with reliable suppliers.
B) reorganize operational processes to organized product lines.
C) train employees to perform various operations.
D) increase raw materials to produce more,thereby increasing finished goods inventory.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
46
____ manufacturing philosophy emphasizes quality and zero defects.

A) Traditional
B) Lean
C) Zero-Based
D) Chinese
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
47
Which of the following drives work-in-process inventory levels higher?

A) Machine breakdowns
B) Production rate losses
C) Rework processes
D) All of the above
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
48
Which of the following is characteristic of a lean production layout?

A) Decentralized maintenance and small production batches
B) Decemtralized maintenance and organization around processes
C) Organization around processes and small production batches
D) Large production batches and organization around processes.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
49
The lean philosophy attempts to reduce setup times,which will:

A) increase batch sizes
B) not affect batch sizes
C) increase within-batch wait time
D) decrease within-batch wait time
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
50
Which of the following is considered non-value-added lead time?

A) packing
B) moving from process to process
C) converting raw materials to finished product
D) all of the above
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
51
What do lean manufacturers demand from their vendors?

A) High quality materials
B) Low cost materials
C) On-time deliveries
D) All of the above
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
52
How are the objectives of lean manufacturing achieved?

A) Product-oriented production layout
B) Employee involvement
C) Supplier partnering
D) All of the above
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
53
Under a lean environment,employees have the responsibility and authority to

A) purchase inventory.
B) determine output amounts.
C) make decisions about operations,rather than waiting for management.
D) make engineering changes.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
54
In a lean environment,process problems are more visible than they are in a traditional environment because:

A) inventories are maintained at higher levels.
B) process problems cause production to shut down immediately.
C) the push manufacturing system leads to increased inventory level.
D) the lack of work in process inventory creates problems.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
55
Which of the following results in long lead time?

A) long setup times
B) large batch sizes
C) large inventories
D) all of the above
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
56
Lean manufacturing philosophy reduces all of the following except

A) inventory
B) setup time
C) lead time
D) conversion costs
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
57
Traditional manufacturing emphasizes all of the following except

A) team oriented employee involvement
B) process-oriented layout
C) push manufacturing
D) cost accumulation by department
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
58
Set up time is disregarded as an improvement priority under the ____ manufacturing concept.

A) traditional
B) lean
C) total quality management
D) product cost
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
59
Which of the following is (are)objective(s)of lean manufacturing?

A) eliminating waste
B) increasing inventory levels
C) increased production speed
D) all of the above
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
60
____ manufacturing deals with several suppliers in hopes of finding the best price.

A) Traditional
B) Lean
C) Economic
D) Productivity improvement
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
61
Financial accounting information is used more often for long-term operating decisions and nonfinancial information is used more often for day-to-day decisions.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
62
A backflush accounting system uses work in process inventories as control points between each process step.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
63
In a lean environment,the journal entry to record conversion costs would include a debit to the raw and in process inventory account.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
64
In a lean system,there are more transactions to record than there are in a traditional system.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
65
In a lean system,the work in process and raw materials inventory accounts are combined.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
66
In a lean system,direct labor is included in conversion costs.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
67
In a lean system,indirect labor is traced directly to product cells.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
68
A nonfinancial measure is operating information that has not been translated into dollars.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
69
In a lean system,there are fewer transactions to record than there are in a traditional system.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
70
A college would like to increase enrollment by streamlining the enrollment process.Which of the following would not fall in line with the college goal?

A) Reduce the requirements necessary to enroll.
B) Relocate counselors,academic advisors,and financial aid specialists for a major to a central location.
C) Cross-train counselors,academic advisors,and financial aid specialists.
D) All of these choices would fall in line with the college goal.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
71
In a lean environment,the journal entry to record raw materials purchases would include a credit to the raw materials inventory account.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
72
The budgeted cell conversion cost rate is very similar to the predetermined factory rate because both include only factory overhead costs.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
73
Nonfinancial accounting information is used more often for long-term operating decisions than is financial information.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
74
Which of the following is characteristic of the lean system?

A) Fewer work in process account transactions.
B) Work in process and raw materials accounts combined.
C) Elimination of the direct labor account.
D) All of the above.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
75
A lean nonmanufacturing process can be accomplished by consolidating,in one area,all of the services provided to a customer.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
76
In a lean environment,the journal entry to record raw materials purchases would include a debit to the raw and in process inventory account.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
77
In a lean environment,the journal entry to record conversion costs would include a debit to the manufacturing overhead control account.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
78
A local college is aggressively working to reduce the time it takes students to enroll for each semester.Which of the following changes would not help achieve this goal?

A) Counselors are specializing in common degree plans
B) One application is good at the community college and at the transferring university
C) A one stop area includes admissions,advising,registration and student ID's
D) Having more number of staff to help facilitate admission process
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
79
Which of the following is characteristic of the traditional cost system?

A) Many work in process account transactions.
B) Reliance on financial performance measures.
C) Many process control points.
D) All of the above.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
80
Extreme Wreaths,Inc.makes wreaths in batch sizes of 15 at a time.The cutting & assembly process takes 10 minutes per wreath,and the decorating process time is 7 minutes per wreath.It takes 5 minutes to move the wreaths from the cutting & assembly process to the decorating process.

In a effort to improve the lead time,the company has tried reducing the batch size to 10 units.The new process is as follows: cutting & assembly process - 8 minutes.The decorating process is still 7 minutes per wreath.It takes 5 minutes to move the wreaths from the cutting & assembly process to the decorating process.

(a)Compute the value-added,non-value-added,and the total lead time of the wreath process for both the old and the new manufacturing process.
(b)Compute the value-added ratio for both the old and new process.Round to the nearest decimal.
Unlock Deck
Unlock for access to all 121 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 121 flashcards in this deck.