Deck 6: The Work Breakdown Structure and Project Estimation

Full screen (f)
exit full mode
Question
The most common error in guesstimating is to be pessimistic and to overestimate the time and resources necessary to complete a project.
Use Space or
up arrow
down arrow
to flip the card.
Question
A work breakdown structure WBS)represents a logical decomposition of the work to be performed and how the product,service,or result is naturally subdivided.
Question
Basing an estimate of activity durations on experience gained from working on similar projects is called analogous estimation.
Question
Each phase of the project should provide at least one specific deliverable.
Question
In much the same fashion as the claim "you can never be too rich",when developing a WBS,one can never have too much detail in planning activities.
Question
Time boxing involves allocating a time segment for a task rather than attempting to estimate how long that task should take.
Question
Because function points are independent of technology,they provide a way to compare projects that may use different platforms or languages.
Question
The Delphi technique is a quick and economical way to estimate the duration and costs of project activities.
Question
The PMBOK area called project time management includes all of the following except:

A)Define Activities
B)Assign Activities
C)Estimate Activity Durations
D)Develop Schedule
E)Control Schedule
Question
The work breakdown structure WBS)decomposes,or subdivides,the project into smaller components and more manageable units of work called work packages.
Question
Which of the following statements about the work breakdown structure WBS)is not ?

A)The WBS provides a hierarchical structure that outlines the activities or work that needs to be done in order to complete the project scope.
B)The WBS should support the project's MOV
C)The WBS should be developed by the project manager.
D)The WBS provides a framework for developing a tactical plan to structure the project work.
E)The WBS provides a bridge or link between the project's scope and the detailed project plan
Question
The 100 percent rule is the most important criterion in the developing and evaluating the WBS.The rule states: "The parent)element must represent 100 percent of the work applicable to next level decomposition of a WBS element child level)."
Question
The use of heuristics is based following immutable principles of project development and lead to highly accurate forecasts.
Question
According to the text,most real-world estimating is made using top-down estimating.
Question
A tangible and verifiable piece of work is called a milestone.
Question
The three major factors in estimating an IT application are: size,complexity,and constraints & influencers.
Question
One way to ensure that the WBS has the appropriate level of detail is to ensure that the people who do the work are involved in its development.
Question
Counting lines of code LOC)is a good way to encourage efficient programming.
Question
COCOMO is an example of a non-parametric model because it is characterized by a usually unlimited set of named parameters.
Question
Research suggests that projects that use a formal estimating tool have a better chance of delivering a system that is on time and within budget.
Question
Confidence in project estimates will be highest _____

A)before the project begins.
B)early in the project.
C)once the team members are assigned.
D)later in the project.
E)when the business case is complete.
Question
_____ can be very effective and provide reasonable assurance when the stakes are high and and the margin of error is low.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
This estimation technique may be driven by an upper management mandate.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
Too much detail in the WBS can lead to _____

A)clearly specified objectives.
B)guaranteed project delivery.
C)time constraints.
D)micromanagement.
E)there can never be too much detail.
Question
A significant event or achievement that provides evidence that a deliverable is complete is called a _____

A)work package
B)phase
C)milestone
D)checkpoint
E)phase gate
Question
With _____,activity estimates are usually provided by the team members.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
In the WBS context,a crux is best described by which of the following:

A)a risk metric
B)a phase gate
C)evidence of a phase completion
D)a deliverable
E)a proof of concept
Question
Project success will be determined in large part by _____

A)familiarity with project management software.
B)producing nice looking reports for management.
C)thinking carefully through activities and estimating their durations.
D)determining exact estimates of activity durations.
E)the skill sets of the project team.
Question
An estimation technique characterized by the dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours,person-weeks,or person-months for each module best describes

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
_____ is the most common,real-world method of estimating projects.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
To be effective,each project phase should provide at least ___ deliverables).

A)one
B)two
C)three
D)as many as needed
E)a project phase does not need to produce a deliverable
Question
_____ focuses on the processes,tools,and methods for developing a quality approach to developing software.

A)Software engineering
B)Metrics
C)Estimation
D)Work Breakdown Structure WBS)
E)Heuristics
Question
The _____ estimation method usually costs more and takes longer than other methods.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
An estimation technique characterized by schedule and cost estimates of how long something should take or should cost.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
An estimation technique characterized by picking numbers out of the air or "ballparking".

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
An estimation technique characterized by the recruitment of multiple experts who provide rounds of estimates until a consensus estimate emerges.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
The 100 percent rule relates to___

A)the next level decomposition of a WBS element must represent 100 percent of the work applicable to the parent element.
B)clearly defining 100 percent of deliverables before beginning the project.
C)ensuring that project requirements remain fully static over the course of the project.
D)everyone's project performance will impact the project.
E)resource requirements needed to complete the project.
Question
The Work Breakdown Structure is subdivided into smaller components called:

A)work packages
B)milestones
C)deliverables
D)tasks
E)activities
Question
_____ can be a very effective estimating technique by forcing examination of project risks so that specific budget or schedule targets can be achieved.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
_____ may result in long hours and frustration for the project team,which may lead to burnout.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Question
A screen that allows the user to input information using a keyboard and a mouse would be called an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Question
Function points in a software application program

A)can be used to illustrate the fact that experienced programmers tend to write more code than novice programmers would in coding the same project.
B)is a superior method of measuring programmer productivity.
C)is simpler because it does not need to consider user requirements.
D)are a high-level analysis of the application requirements.
E)focus on the functionality and complexity of an application system or module.
Question
What is the Delphi technique? When would it be an appropriate estimating technique for an IT project?
Question
Describe the PMBOK area of project time management.
Question
What is a work package?
Question
An entity in an Entity-Relationship Diagram ERD)would be considered an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Question
A management report and its accompanying graphs would be considered an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Question
With COCOMO,_____ projects are routine where the technology,processes,and people are expected to work together smoothly.

A)organic
B)embedded
C)detached
D)semi-detached
E)restrained
Question
With COCOMO,_____ projects are somewhat challenge and may integrate new processes and technology.

A)organic
B)embedded
C)detached
D)semi-detached
E)restrained
Question
The first step in accurately estimating an IT application is to _____.

A)determine the size
B)determine available resources
C)determine project budget
D)set the project deadline
E)determine project constraints
Question
What is a WBS? What purpose does it serve?
Question
Explain why people who do the work on a project should be involved in developing the project plan?
Question
What is the proper level of detail for a WBS?
Question
What is guesstimating? Why should a project manager not rely on this technique for estimating a project?
Question
_____ is a parametric model using dependent variables based upon one or more independent variables that are measures of performance or physical attributes of the system.

A)COCOMO
B)LOC
C)HEURISTICS.
D)CHECKPOINT
E)SLIM
Question
An entity or data set that includes customer names and addresses that is maintained by another application system would be called an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input process EI)
D)External Output EO)
E)External Inquiry EQ)
Question
With COCOMO,_____ projects are challenging in that they may support a new business process or area that is new to the organization.

A)organic
B)embedded
C)detached
D)semi-detached
E)restrained
Question
Something that includes a combination of inputs and outputs for retrieving data from either the internal files or from files external to the application would be called an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Question
LOC in a software application program

A)can be used to illustrate the fact that experienced programmers tend to write more code than novice programmers would in coding the same project.
B)is a superior method of measuring programmer productivity.
C)would have a similar value for a program written in Assembler as would the same program written in Visual Basic.
D)is easier to count once the program is written than it is to estimate how many lines of code will be actually required to write the program.
E)takes into account the complexity,constraints,and influencers of a project.
Question
_____ refers to a broad range of measurements for objectively evaluating computer software.

A)Software engineering
B)Metrics
C)Estimation
D)Work Breakdown Structure WBS)
E)Heuristics
Question
Describe top-down estimating.What are some advantages and disadvantages of top-down estimating?
Question
What is time boxing? What are some advantages and disadvantages of time boxing project activities?
Question
Under the COCOMO model,describe the organic,semi-detached,and embedded models.
Question
Describe bottom-up estimating.What are some advantages and disadvantages of bottom-up estimating?
Question
How can function point analysis be used to help manage scope creep?
Question
What is a function point? What advantages do function points have over counting lines of code?
Unlock Deck
Sign up to unlock the cards in this deck!
Unlock Deck
Unlock Deck
1/66
auto play flashcards
Play
simple tutorial
Full screen (f)
exit full mode
Deck 6: The Work Breakdown Structure and Project Estimation
1
The most common error in guesstimating is to be pessimistic and to overestimate the time and resources necessary to complete a project.
False
2
A work breakdown structure WBS)represents a logical decomposition of the work to be performed and how the product,service,or result is naturally subdivided.
True
3
Basing an estimate of activity durations on experience gained from working on similar projects is called analogous estimation.
True
4
Each phase of the project should provide at least one specific deliverable.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
5
In much the same fashion as the claim "you can never be too rich",when developing a WBS,one can never have too much detail in planning activities.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
6
Time boxing involves allocating a time segment for a task rather than attempting to estimate how long that task should take.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
7
Because function points are independent of technology,they provide a way to compare projects that may use different platforms or languages.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
8
The Delphi technique is a quick and economical way to estimate the duration and costs of project activities.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
9
The PMBOK area called project time management includes all of the following except:

A)Define Activities
B)Assign Activities
C)Estimate Activity Durations
D)Develop Schedule
E)Control Schedule
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
10
The work breakdown structure WBS)decomposes,or subdivides,the project into smaller components and more manageable units of work called work packages.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
11
Which of the following statements about the work breakdown structure WBS)is not ?

A)The WBS provides a hierarchical structure that outlines the activities or work that needs to be done in order to complete the project scope.
B)The WBS should support the project's MOV
C)The WBS should be developed by the project manager.
D)The WBS provides a framework for developing a tactical plan to structure the project work.
E)The WBS provides a bridge or link between the project's scope and the detailed project plan
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
12
The 100 percent rule is the most important criterion in the developing and evaluating the WBS.The rule states: "The parent)element must represent 100 percent of the work applicable to next level decomposition of a WBS element child level)."
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
13
The use of heuristics is based following immutable principles of project development and lead to highly accurate forecasts.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
14
According to the text,most real-world estimating is made using top-down estimating.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
15
A tangible and verifiable piece of work is called a milestone.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
16
The three major factors in estimating an IT application are: size,complexity,and constraints & influencers.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
17
One way to ensure that the WBS has the appropriate level of detail is to ensure that the people who do the work are involved in its development.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
18
Counting lines of code LOC)is a good way to encourage efficient programming.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
19
COCOMO is an example of a non-parametric model because it is characterized by a usually unlimited set of named parameters.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
20
Research suggests that projects that use a formal estimating tool have a better chance of delivering a system that is on time and within budget.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
21
Confidence in project estimates will be highest _____

A)before the project begins.
B)early in the project.
C)once the team members are assigned.
D)later in the project.
E)when the business case is complete.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
22
_____ can be very effective and provide reasonable assurance when the stakes are high and and the margin of error is low.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
23
This estimation technique may be driven by an upper management mandate.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
24
Too much detail in the WBS can lead to _____

A)clearly specified objectives.
B)guaranteed project delivery.
C)time constraints.
D)micromanagement.
E)there can never be too much detail.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
25
A significant event or achievement that provides evidence that a deliverable is complete is called a _____

A)work package
B)phase
C)milestone
D)checkpoint
E)phase gate
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
26
With _____,activity estimates are usually provided by the team members.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
27
In the WBS context,a crux is best described by which of the following:

A)a risk metric
B)a phase gate
C)evidence of a phase completion
D)a deliverable
E)a proof of concept
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
28
Project success will be determined in large part by _____

A)familiarity with project management software.
B)producing nice looking reports for management.
C)thinking carefully through activities and estimating their durations.
D)determining exact estimates of activity durations.
E)the skill sets of the project team.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
29
An estimation technique characterized by the dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours,person-weeks,or person-months for each module best describes

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
30
_____ is the most common,real-world method of estimating projects.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
31
To be effective,each project phase should provide at least ___ deliverables).

A)one
B)two
C)three
D)as many as needed
E)a project phase does not need to produce a deliverable
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
32
_____ focuses on the processes,tools,and methods for developing a quality approach to developing software.

A)Software engineering
B)Metrics
C)Estimation
D)Work Breakdown Structure WBS)
E)Heuristics
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
33
The _____ estimation method usually costs more and takes longer than other methods.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
34
An estimation technique characterized by schedule and cost estimates of how long something should take or should cost.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
35
An estimation technique characterized by picking numbers out of the air or "ballparking".

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
36
An estimation technique characterized by the recruitment of multiple experts who provide rounds of estimates until a consensus estimate emerges.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
37
The 100 percent rule relates to___

A)the next level decomposition of a WBS element must represent 100 percent of the work applicable to the parent element.
B)clearly defining 100 percent of deliverables before beginning the project.
C)ensuring that project requirements remain fully static over the course of the project.
D)everyone's project performance will impact the project.
E)resource requirements needed to complete the project.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
38
The Work Breakdown Structure is subdivided into smaller components called:

A)work packages
B)milestones
C)deliverables
D)tasks
E)activities
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
39
_____ can be a very effective estimating technique by forcing examination of project risks so that specific budget or schedule targets can be achieved.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
40
_____ may result in long hours and frustration for the project team,which may lead to burnout.

A)Guesstimating
B)Delphi Technique
C)Time Boxing
D)Top-Down Estimating
E)Bottom-Up Estimating
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
41
A screen that allows the user to input information using a keyboard and a mouse would be called an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
42
Function points in a software application program

A)can be used to illustrate the fact that experienced programmers tend to write more code than novice programmers would in coding the same project.
B)is a superior method of measuring programmer productivity.
C)is simpler because it does not need to consider user requirements.
D)are a high-level analysis of the application requirements.
E)focus on the functionality and complexity of an application system or module.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
43
What is the Delphi technique? When would it be an appropriate estimating technique for an IT project?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
44
Describe the PMBOK area of project time management.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
45
What is a work package?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
46
An entity in an Entity-Relationship Diagram ERD)would be considered an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
47
A management report and its accompanying graphs would be considered an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
48
With COCOMO,_____ projects are routine where the technology,processes,and people are expected to work together smoothly.

A)organic
B)embedded
C)detached
D)semi-detached
E)restrained
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
49
With COCOMO,_____ projects are somewhat challenge and may integrate new processes and technology.

A)organic
B)embedded
C)detached
D)semi-detached
E)restrained
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
50
The first step in accurately estimating an IT application is to _____.

A)determine the size
B)determine available resources
C)determine project budget
D)set the project deadline
E)determine project constraints
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
51
What is a WBS? What purpose does it serve?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
52
Explain why people who do the work on a project should be involved in developing the project plan?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
53
What is the proper level of detail for a WBS?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
54
What is guesstimating? Why should a project manager not rely on this technique for estimating a project?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
55
_____ is a parametric model using dependent variables based upon one or more independent variables that are measures of performance or physical attributes of the system.

A)COCOMO
B)LOC
C)HEURISTICS.
D)CHECKPOINT
E)SLIM
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
56
An entity or data set that includes customer names and addresses that is maintained by another application system would be called an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input process EI)
D)External Output EO)
E)External Inquiry EQ)
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
57
With COCOMO,_____ projects are challenging in that they may support a new business process or area that is new to the organization.

A)organic
B)embedded
C)detached
D)semi-detached
E)restrained
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
58
Something that includes a combination of inputs and outputs for retrieving data from either the internal files or from files external to the application would be called an:

A)Internal Logical File ILF)
B)External Interface File EIF)
C)External Input EI)
D)External Output EO)
E)External Inquiry EQ)
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
59
LOC in a software application program

A)can be used to illustrate the fact that experienced programmers tend to write more code than novice programmers would in coding the same project.
B)is a superior method of measuring programmer productivity.
C)would have a similar value for a program written in Assembler as would the same program written in Visual Basic.
D)is easier to count once the program is written than it is to estimate how many lines of code will be actually required to write the program.
E)takes into account the complexity,constraints,and influencers of a project.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
60
_____ refers to a broad range of measurements for objectively evaluating computer software.

A)Software engineering
B)Metrics
C)Estimation
D)Work Breakdown Structure WBS)
E)Heuristics
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
61
Describe top-down estimating.What are some advantages and disadvantages of top-down estimating?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
62
What is time boxing? What are some advantages and disadvantages of time boxing project activities?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
63
Under the COCOMO model,describe the organic,semi-detached,and embedded models.
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
64
Describe bottom-up estimating.What are some advantages and disadvantages of bottom-up estimating?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
65
How can function point analysis be used to help manage scope creep?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
66
What is a function point? What advantages do function points have over counting lines of code?
Unlock Deck
Unlock for access to all 66 flashcards in this deck.
Unlock Deck
k this deck
locked card icon
Unlock Deck
Unlock for access to all 66 flashcards in this deck.