Exam 6: The Work Breakdown Structure and Project Estimation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In the WBS context,a crux is best described by which of the following:

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
Verified

E

Explain why people who do the work on a project should be involved in developing the project plan?

Free
(Essay)
4.8/5
(32)
Correct Answer:
Verified

Developing the WBS may require several versions until everyone is comfortable and confident that all of the work activities have been included.It is also a good idea to involve those who will be doing the work-after all,they probably know what has to be done better than anyone else.

The 100 percent rule relates to___

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
Verified

A

_____ refers to a broad range of measurements for objectively evaluating computer software.

(Multiple Choice)
4.9/5
(36)

COCOMO is an example of a non-parametric model because it is characterized by a usually unlimited set of named parameters.

(True/False)
4.7/5
(36)

Under the COCOMO model,describe the organic,semi-detached,and embedded models.

(Essay)
4.9/5
(42)

Confidence in project estimates will be highest _____

(Multiple Choice)
4.9/5
(33)

Describe bottom-up estimating.What are some advantages and disadvantages of bottom-up estimating?

(Essay)
4.7/5
(28)

_____ focuses on the processes,tools,and methods for developing a quality approach to developing software.

(Multiple Choice)
4.8/5
(38)

_____ is the most common,real-world method of estimating projects.

(Multiple Choice)
4.9/5
(40)

Which of the following statements about the work breakdown structure WBS)is not ?

(Multiple Choice)
5.0/5
(40)

Each phase of the project should provide at least one specific deliverable.

(True/False)
4.8/5
(31)

LOC in a software application program

(Multiple Choice)
4.8/5
(40)

A management report and its accompanying graphs would be considered an:

(Multiple Choice)
5.0/5
(29)

_____ can be a very effective estimating technique by forcing examination of project risks so that specific budget or schedule targets can be achieved.

(Multiple Choice)
4.7/5
(32)

What is guesstimating? Why should a project manager not rely on this technique for estimating a project?

(Essay)
4.9/5
(36)

With COCOMO,_____ projects are routine where the technology,processes,and people are expected to work together smoothly.

(Multiple Choice)
4.8/5
(30)

An entity or data set that includes customer names and addresses that is maintained by another application system would be called an:

(Multiple Choice)
4.8/5
(33)

Describe top-down estimating.What are some advantages and disadvantages of top-down estimating?

(Essay)
4.8/5
(30)

The three major factors in estimating an IT application are: size,complexity,and constraints & influencers.

(True/False)
4.7/5
(26)
Showing 1 - 20 of 66