Exam 12: Standard Costs and Balanced Scorecard
Exam 1: Managerial Accounting100 Questions
Exam 2: Managerial Cost Concepts and Cost Behaviour Analysis98 Questions
Exam 3: Job Order Costing166 Questions
Exam 4: Process Costing65 Questions
Exam 5: Activity-Based-Costing81 Questions
Exam 6: Cost-Volume-Profit78 Questions
Exam 7: Incremental Analysis103 Questions
Exam 8: Variable Costing: a Decision-Making Perspective57 Questions
Exam 9: Pricing102 Questions
Exam 10: Budgetary Planning155 Questions
Exam 11: Budgetary Control and Responsibility Accounting110 Questions
Exam 12: Standard Costs and Balanced Scorecard101 Questions
Exam 13: Planning for Capital Investments100 Questions
Select questions type
Standard cost + price variance + quantity variance = Budgeted cost.
(True/False)
4.9/5
(36)
The difference between fixed overhead budgeted and overhead applied is the
(Multiple Choice)
4.8/5
(25)
An advantage of standard costs is that they simplify costing of inventories and reduce clerical costs.
(True/False)
4.8/5
(41)
If the labour quantity variance is unfavourable and the cause is inefficient use of direct labour, the responsibility rests with the
(Multiple Choice)
4.7/5
(29)
Manufacturing overhead costs are applied to work in process on the basis of
(Multiple Choice)
4.9/5
(41)
Use the following information for questions
Bridgeware Company has a materials price standard of $2.50 per kilogram.Four thousand kilograms of materials were purchased at $2.40 a kilogram.The actual quantity of materials used was 3,500 kilograms, although the standard quantity allowed for the output was 3,400 kilograms.
-Bridgeware Company's total materials variance is
(Multiple Choice)
4.8/5
(29)
The fixed overhead volume variance relates only to fixed overhead costs.
(True/False)
4.8/5
(36)
An overhead fixed volume variance is calculated as the difference between normal capacity hours and standard hours allowed
(Multiple Choice)
4.9/5
(35)
If actual costs are less than standard costs, the variance is favourable.
(True/False)
4.9/5
(43)
The direct materials quantity standard would not be expressed in
(Multiple Choice)
4.8/5
(35)
The standard number of hours that should have been worked for the output attained is 8,000 direct labour hours and the actual number of direct labour hours worked was 8,400.If the direct labour price variance was $8,400 unfavourable, and the standard rate of pay was $18 per direct labour hour, what was the actual rate of pay for direct labour?
(Multiple Choice)
4.9/5
(39)
If actual direct material costs are greater than standard direct materials costs, it means that
(Multiple Choice)
4.9/5
(37)
Setting standard costs is relatively simple because it is done entirely by accountants.
(True/False)
4.8/5
(32)
The fixed overhead variance that indicates whether plant facilities were efficiently used is the
(Multiple Choice)
4.9/5
(30)
Showing 61 - 80 of 101
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)