The time required for the PLC to complete one scan (read inputs, solve logic, and update outputs) is called the scan time. A typical value for scan time is in the order of ____.

Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
Verified

A

By definition, ____________________ devices are all devices outside the processor, including all hardware.

Free
(Short Answer)
4.9/5
(34)
Correct Answer:
Verified

peripheral

The input signal must be converted to a(n) ____ logic voltage for use in the processor.

Free
(Multiple Choice)
4.8/5
(45)
Correct Answer:
Verified

D

In industrial applications where the PLC will replace the relay logic circuit, the operator controls and process switches will generally remain as they are wired.

(True/False)
4.8/5
(35)

Through a sophisticated system of digital signal transmission and reception, binary data can be organized in a structured format called a(n) ____.

(Multiple Choice)
4.8/5
(44)

The most common PLC programming language used in industry is called ____________________.

(Short Answer)
4.7/5
(42)

Volatile memory will lose its programmed contents if operating power is removed or lost.

(True/False)
5.0/5
(42)

The only devices in the decision maker category for the PLC system are the ___________________ that reside in the PLC logic program.

(Short Answer)
4.7/5
(34)

A PLC system offers many advantages over a relay-based control system except that it can be difficult to implement.

(True/False)
4.9/5
(39)

The compilation of all available instructions for a given PLC is called the ____.

(Multiple Choice)