Exam 10: The Resource Interface
Exam 1: Introduction: Projecting the Modern World14 Questions
Exam 2: The Three Domains of Project Organizing23 Questions
Exam 3: Leading16 Questions
Exam 4: Visioning and Inventing15 Questions
Exam 5: The Owner Domain9 Questions
Exam 6: The Supplier Domain16 Questions
Exam 7: The Delivery Domain17 Questions
Exam 8: The Governance Interface15 Questions
Exam 9: The Commercial Interface18 Questions
Exam 10: The Resource Interface18 Questions
Exam 11: The Core Skills16 Questions
Exam 12: Being a Project Leader12 Questions
Select questions type
Matching
Within the project matrix, the balance between the responsibility of the project managers compared to the resource-base managers varies across different projects:
-Lightweight project organization
Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
B
Matching
Within the project matrix, the balance between the responsibility of the project managers compared to the resource-base managers varies across different projects:
-Functional project organization
Free
(Multiple Choice)
4.9/5
(30)
Correct Answer:
A
Matching
While utilizing knowledge as a resource is essential in SPO, and many organizations have established strategies for its acquisition and deployment, these often remain ineffective for a number of reasons:
-Centralization
Free
(Multiple Choice)
4.8/5
(40)
Correct Answer:
C
Matching
Resources are allocated to the project structure resulting from the design by the PBFs from their resource-based. A valuable tool for doing this is the RACI chart which consists of:
-C
(Multiple Choice)
4.8/5
(38)
Regions - typically major cities - where the human resources required for the delivery of projects congregate :
(Multiple Choice)
4.8/5
(38)
The allocation of human resources to project delivery organizations generates considerable tensions as project managers and resource-base managers compete for resources.
(True/False)
4.7/5
(38)
Matching
While utilizing knowledge as a resource is essential in SPO, and many organizations have established strategies for its acquisition and deployment, these often remain ineffective for a number of reasons:
-Time
(Multiple Choice)
4.7/5
(39)
Matching
Resources are allocated to the project structure resulting from the design by the PBFs from their resource-based. A valuable tool for doing this is the RACI chart which consists of:
-I
(Multiple Choice)
4.8/5
(39)
In the RACI chart, the difference between Responsible and Accountable is important. The Accountable person organizes execution of the task and leads the task execution team, while the Responsible person appoints the A-person, and ensures that the A-person delivers.
(True/False)
4.8/5
(44)
Knowledge that is fully communicable between any two or more individuals. Knowledge that can be traded internationally in the form of intellectual property, or it can be held in secret as proprietary knowledge to gain competitive advantage:
(Multiple Choice)
4.9/5
(42)
The financial resources required for project delivery come from the supplier domain but the human and technological resources required are the responsibilities of the owner domain.
(True/False)
4.9/5
(30)
The agile working methods should ease resource allocation tensions because they eliminate the problem of schedule overrun and hence the retention of resources by a particular project when they are needed on another project.
(True/False)
4.8/5
(36)
Matching
While utilizing knowledge as a resource is essential in SPO, and many organizations have established strategies for its acquisition and deployment, these often remain ineffective for a number of reasons:
-Incentives
(Multiple Choice)
4.9/5
(32)
Matching
Within the project matrix, the balance between the responsibility of the project managers compared to the resource-base managers varies across different projects:
-Autonomous project organization
(Multiple Choice)
4.8/5
(29)
Matching
Resources are allocated to the project structure resulting from the design by the PBFs from their resource-based. A valuable tool for doing this is the RACI chart which consists of:
-R
(Multiple Choice)
4.8/5
(37)
Matching
Resources are allocated to the project structure resulting from the design by the PBFs from their resource-based. A valuable tool for doing this is the RACI chart which consists of:
-A
(Multiple Choice)
4.9/5
(34)
Matching
Within the project matrix, the balance between the responsibility of the project managers compared to the resource-base managers varies across different projects: