Exam 7: Monitoring and Controlling the Project
Exam 1: The World of Project Management52 Questions
Exam 2: The Manager, the Organization, and the Team45 Questions
Exam 3: Planning the Project48 Questions
Exam 4: Budgeting the Project46 Questions
Exam 5: Scheduling the Project46 Questions
Exam 6: Allocating Resources to the Project46 Questions
Exam 7: Monitoring and Controlling the Project45 Questions
Exam 8: Evaluating and Terminating the Project45 Questions
Select questions type
Raw numbers represent a simple tally of the occurrence of an event.
Free
(True/False)
4.9/5
(37)
Correct Answer:
False
The cost/spending variance is calculated as
Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
E
Frequent blame is considered a good motivational tool to keep project team members on track.
Free
(True/False)
4.8/5
(29)
Correct Answer:
False
Which of the following is most closely associated with ordinal rankings?
(Multiple Choice)
4.7/5
(35)
Everyone associated with the project should receive the same information.
(True/False)
4.9/5
(41)
Control is the collection,recording,and reporting of project information.
(True/False)
4.8/5
(27)
A common mistake is to focus too much on results and not enough on the intensity of activity.
(True/False)
4.9/5
(36)
Exception reports are prepared to disseminate the results of a special study.
(True/False)
4.8/5
(37)
In order to manage for overall project success,control must be exercised at the detailed work level for each aspect of project performance.
(True/False)
4.8/5
(37)
Estimated (remaining cost)to completion (ETC)is calculated as
(Multiple Choice)
4.8/5
(38)
Which of the following is NOT a primary mechanism by which the PM exerts control?
(Multiple Choice)
4.8/5
(40)
The most important use of data gathered from monitoring is learning from mistakes.
(True/False)
4.9/5
(27)
An important use of data analysis is to identify who to properly blame for poor project performance.
(True/False)
4.7/5
(31)
The percentage of an activity's budget actually spent by a given date is typically a good indicator of the percent of that activity's completion.
(True/False)
4.8/5
(39)
Which of the following is NOT a component of a control system?
(Multiple Choice)
4.9/5
(46)
The purpose of control is to ensure that all interested parties have the information they need.
(True/False)
4.8/5
(38)
Showing 1 - 20 of 45
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)