Raw numbers represent a simple tally of the occurrence of an event.

Free
(True/False)
4.9/5
(37)
Correct Answer:
Verified

False

The cost/spending variance is calculated as

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
Verified

E

Frequent blame is considered a good motivational tool to keep project team members on track.

Free
(True/False)
4.8/5
(29)
Correct Answer:
Verified

False

Which of the following is NOT a distinct type of report?

(Multiple Choice)
4.9/5
(31)

Which of the following is most closely associated with ordinal rankings?

(Multiple Choice)
4.7/5
(35)

The plan-monitor-control cycle is best described as

(Multiple Choice)
4.8/5
(44)

Everyone associated with the project should receive the same information.

(True/False)
4.9/5
(41)

Control is the collection,recording,and reporting of project information.

(True/False)
4.8/5
(27)

A common mistake is to focus too much on results and not enough on the intensity of activity.

(True/False)
4.9/5
(36)

Exception reports are prepared to disseminate the results of a special study.

(True/False)
4.8/5
(37)

In order to manage for overall project success,control must be exercised at the detailed work level for each aspect of project performance.

(True/False)
4.8/5
(37)

Estimated (remaining cost)to completion (ETC)is calculated as

(Multiple Choice)
4.8/5
(38)

Which of the following is NOT a primary mechanism by which the PM exerts control?

(Multiple Choice)
4.8/5
(40)

The most important use of data gathered from monitoring is learning from mistakes.

(True/False)
4.9/5
(27)

Weekly progress report meetings should be rarely held.

(True/False)
4.9/5
(40)

An important use of data analysis is to identify who to properly blame for poor project performance.

(True/False)
4.7/5
(31)

In general,it is preferable to have periodic reports.

(True/False)
4.8/5
(41)

The percentage of an activity's budget actually spent by a given date is typically a good indicator of the percent of that activity's completion.

(True/False)
4.8/5
(39)

Which of the following is NOT a component of a control system?

(Multiple Choice)
4.9/5
(46)

The purpose of control is to ensure that all interested parties have the information they need.

(True/False)
4.8/5
(38)