Question 46

Question 46

Multiple Choice

The cost/spending variance is calculated as…


A) AC - EV
B) EV - PV
C) PV - EV
D) AC - PV
E) EV - AC

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: The concept of earned value (EV) is

Q42: One way of linking planning and control

Q43: Physical asset control is concerned with the

Q44: With Agile approaches, project scope is assumed

Q45: An important use of data analysis is

Q47: Only senior scrum team members participate in

Q48: Paulina, a fashion designer, has a new

Q49: The most common source of changes to

Q50: Earned value is a measure for overall

Q51: David, an architect, is in charge of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines